Prev: In Project 2007, Group By Baseline Start is Rolling Up Max, not Mi
Next: How do I Set reminder within Project XP to appear in Outlook
From: laguna on 4 Mar 2010 12:50 We're using PS 2007. For some reason LastStatusChangeResourceNameUID in Timesheet table is NULL. It prevents me from identifying surrogate timesheets. What do I need to do to make this field populate when Resource Manager submits timesheet for his resource?
From: Andrew Lavinsky on 4 Mar 2010 13:06
You'll have better luck posting to the Project Server newsgroup. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > We're using PS 2007. For some reason LastStatusChangeResourceNameUID > in Timesheet table is NULL. It prevents me from identifying surrogate > timesheets. What do I need to do to make this field populate when > Resource Manager submits timesheet for his resource? > |