From: Jim Aksel on
It will use what ever calendar is assigned to task B. If B has no assigned
calendar the the project calendar is used.

To check calendars:

Project Calendar: On the menu: Project/Project Information. The default is
"Standard"
For a task, double click the task to view the Task Information dialog box.
Pull the Advanced tab and look under Calendar. If the task calendar is
"none" then it is using the Project Calendar.
--
Jim Aksel, MVP

Check my blog for more info:
http://www.msprojectblog.com

This newsgroup is moving, try here too:
http://social.answers.microsoft.com/Forums/en-US/addbuz/threads