From: DanM on 27 May 2010 04:30 Hello, Can any one tell me witch calendar the lag is using? What I mean is: I have 2 activities. A and B, A is driving B with a lag. A has one calendar and B has another calendar. Witch calendar is the lag using? Regards Dan -- DanM ------------------------------------------------------------------------ DanM's Profile: http://forums.techarena.in/members/184017.htm View this thread: http://forums.techarena.in/microsoft-project/1341063.htm http://forums.techarena.in
From: Jan De Messemaeker on 27 May 2010 05:08 Hi, B's calendar. Greetings, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "DanM" <DanM.4bm49c(a)DoNotSpam.com> wrote in message news:DanM.4bm49c(a)DoNotSpam.com... > > Hello, > > Can any one tell me witch calendar the lag is using? > > What I mean is: > > I have 2 activities. A and B, A is driving B with a lag. A has one > calendar and B has another calendar. Witch calendar is the lag using? > > Regards > > Dan > > > -- > DanM > ------------------------------------------------------------------------ > DanM's Profile: http://forums.techarena.in/members/184017.htm > View this thread: http://forums.techarena.in/microsoft-project/1341063.htm > > http://forums.techarena.in >
From: DanM on 27 May 2010 08:06 With B�s Calendar, do you mean base calendar? Thank you for a fast reply Regards Dan -- DanM ------------------------------------------------------------------------ DanM's Profile: http://forums.techarena.in/members/184017.htm View this thread: http://forums.techarena.in/microsoft-project/1341063.htm http://forums.techarena.in
From: salgud on 27 May 2010 10:02 On Thu, 27 May 2010 07:06:53 -0500, DanM wrote: > With B�s Calendar, do you mean base calendar? > > Thank you for a fast reply > > Regards > > Dan Very confusing! He meant Base Calendar.
From: Jim Aksel on 27 May 2010 15:53 Microsoft Project uses the following types of calendars to determine resource availability and the way tasks are scheduled: Base calendar A base calendar is used as a *template* that the project calendar (project calendar: The base calendar used by a project.), resource calendars or task calendars are based on. Three base calendars are provided with Project: •Standard (8:00 A.M. to 5:00 P.M. weekdays, with an hour off for lunch) •24-Hours •Night Shift So the base calendar is the template. If you make a new calendar, base it off one of these. By default, the Standard calendar is assigned as the Project Calendar for projects and project tasks. What we do is make a copy of the Standard Calendar and call it "Company Calendar". We input company holidays, shut down time, etc. We then assign "Company Calendar" as the "Project Calendar" in Project/Project Options... So to directly answer the question, the calendar assigned to predecessor is the calendar of the successor (Task B). If Task B does not have a calendar assigned to it, then project uses the same calendar that appears in Project/Project Options. If that calendar name happens to be one of the three base calendar names, then so be it. The point is subtle and probably I am being Nit Picky ... at any rate, I gave you the two places to look for the calendar that will govern how lag is handled in a predecessor/successor relationship. -- Jim Aksel, MVP Check my blog for more info: http://www.msprojectblog.com This newsgroup is moving, try here too: http://social.answers.microsoft.com/Forums/en-US/addbuz/threads "DanM" wrote: > > With B´s Calendar, do you mean base calendar? > > Thank you for a fast reply > > Regards > > Dan > > > -- > DanM > ------------------------------------------------------------------------ > DanM's Profile: http://forums.techarena.in/members/184017.htm > View this thread: http://forums.techarena.in/microsoft-project/1341063.htm > > http://forums.techarena.in > > . >
|
Next
|
Last
Pages: 1 2 Prev: Resources, tasks, dates, remaining work view Next: Start to Finish relationship |