Hello friends,

Have a problem leveling resources is the follow:

Bob task1 4hs day1
Bob task2 6hs day2

I need to add more task for BoB filling the time avaliable

Bob task1 4hs day1
Bob task2 6hs day2
Bob Taks3 4hs day1 and 2hs day2

Is this possible? shall I to do a macro ?


Thanks in advance and sorry by my english,
Christian W.

From: John on
In article <1D4AA9D3-9733-40BB-96F5-4EF9EF6A973F(a)microsoft.com>,
Christian W <ChristianW(a)discussions.microsoft.com> wrote:

> Hello friends,
>
> Have a problem leveling resources is the follow:
>
> Bob task1 4hs day1
> Bob task2 6hs day2
>
> I need to add more task for BoB filling the time avaliable
>
> Bob task1 4hs day1
> Bob task2 6hs day2
> Bob Taks3 4hs day1 and 2hs day2
>
> Is this possible? shall I to do a macro ?
>
>
> Thanks in advance and sorry by my english,
> Christian W.

Christian,
The primary reason for using the leveling feature of Project is to move
tasks based on priority for resources that are overallocated. The
leveling feature will NOT create tasks to fill in gaps of free time for
resources.

Is it possible to find more work to fill in Bob's spare time? Probably,
but it depends on Bob's supervisor/management to find and assign
suitable work. Could you write a macro to do that? Maybe, but assigning
the right resources to do required work requires a whole lot of
subjective assessment on the part of the project manager - not something
that is easily implemented in a macro.

John
Project MVP
From: Trevor Rabey on
This is not about leveling.
How do you define leveling?

This just filling up available slots.
Use the Task Usage View to set Work hours for each day.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
news:1D4AA9D3-9733-40BB-96F5-4EF9EF6A973F(a)microsoft.com...
> Hello friends,
>
> Have a problem leveling resources is the follow:
>
> Bob task1 4hs day1
> Bob task2 6hs day2
>
> I need to add more task for BoB filling the time avaliable
>
> Bob task1 4hs day1
> Bob task2 6hs day2
> Bob Taks3 4hs day1 and 2hs day2
>
> Is this possible? shall I to do a macro ?
>
>
> Thanks in advance and sorry by my english,
> Christian W.
>


From: Jan De Messemaeker on
Hi Christian,

I already answered this.
I hope you will read the answer this time.
Set all tasks such that units are 100%
So task 1 duration 4 hours, Work 4 hours
Task 2 duration 6 hours, Work 6 hours, start day2
Task 3 duration 6 hours, work 6 hours

In Leveling make sure "Leveling can split tasks" is ON
Make Sure Task 3 has a lower priority that 1 and 2
Leveling order Priority, Standard.

Now level.

A macro can only automate whet you do manually, it does not add features.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
news:1D4AA9D3-9733-40BB-96F5-4EF9EF6A973F(a)microsoft.com...
> Hello friends,
>
> Have a problem leveling resources is the follow:
>
> Bob task1 4hs day1
> Bob task2 6hs day2
>
> I need to add more task for BoB filling the time avaliable
>
> Bob task1 4hs day1
> Bob task2 6hs day2
> Bob Taks3 4hs day1 and 2hs day2
>
> Is this possible? shall I to do a macro ?
>
>
> Thanks in advance and sorry by my english,
> Christian W.
>


From: Jan De Messemaeker on
Hi Trevor,

Why do manually what the software can do?
Filling slots may be a good use for leveling, why not?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Trevor Rabey" <trevorATperfectproject.com.au> wrote in message
news:pe6dnfGCaP8n6D3WnZ2dnUVZ8hOdnZ2d(a)westnet.com.au...
> This is not about leveling.
> How do you define leveling?
>
> This just filling up available slots.
> Use the Task Usage View to set Work hours for each day.
> --
> Trevor Rabey
> 0407213955
> 61 8 92727485
> PERFECT PROJECT PLANNING
> www.perfectproject.com.au
>
> "Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
> news:1D4AA9D3-9733-40BB-96F5-4EF9EF6A973F(a)microsoft.com...
>> Hello friends,
>>
>> Have a problem leveling resources is the follow:
>>
>> Bob task1 4hs day1
>> Bob task2 6hs day2
>>
>> I need to add more task for BoB filling the time avaliable
>>
>> Bob task1 4hs day1
>> Bob task2 6hs day2
>> Bob Taks3 4hs day1 and 2hs day2
>>
>> Is this possible? shall I to do a macro ?
>>
>>
>> Thanks in advance and sorry by my english,
>> Christian W.
>>
>
>