From: Edward on 1 Apr 2010 10:29 Hi, all How can I insert an one year task duration in Project (time unit 1y don't work)? Thanks ---------------- Edward
From: Dale Howard [MVP] on 1 Apr 2010 11:32 Edward -- How about entering 52w as the Duration? -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Edward(a)BR" <EdwardBR(a)discussions.microsoft.com> wrote in message news:577E64DB-4E8C-4FF6-8B84-599530D917CA(a)microsoft.com... > Hi, all > > How can I insert an one year task duration in Project (time unit 1y don't > work)? > > Thanks > ---------------- > Edward
From: Edward on 1 Apr 2010 13:37 Hi, Dale Ok, this is a solution. But the question is: why the option at Tools, Options, Edit > View options for time units in ... ? It's really don't works? It's a bug? Thanks ---------------- Edward "Dale Howard [MVP]" escreveu: > Edward -- > > How about entering 52w as the Duration? > > -- > Dale A. Howard [MVP] > VP of Educational Services > msProjectExperts > http://www.msprojectexperts.com > http://www.projectserverexperts.com > "We write the books on Project Server" > > > "Edward(a)BR" <EdwardBR(a)discussions.microsoft.com> wrote in message > news:577E64DB-4E8C-4FF6-8B84-599530D917CA(a)microsoft.com... > > Hi, all > > > > How can I insert an one year task duration in Project (time unit 1y don't > > work)? > > > > Thanks > > ---------------- > > Edward >
From: Dale Howard [MVP] on 1 Apr 2010 13:47 Edward -- When I attempt to enter a Duration value in years, such as "1y" I get a warning message and the system does not allow me to enter the desired Duration value. I would suspect it is a bug, but only Microsoft staff would know for sure. It doesn't work in Project 2010 either, and I don't know any workaround. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Edward(a)BR" <EdwardBR(a)discussions.microsoft.com> wrote in message news:84D4610A-DC67-4882-B77F-395D4A906B5D(a)microsoft.com... > Hi, Dale > > Ok, this is a solution. > But the question is: why the option at Tools, Options, Edit > View options > for time units in ... ? > It's really don't works? It's a bug? > > Thanks > ---------------- > Edward > > > "Dale Howard [MVP]" escreveu: > >> Edward -- >> >> How about entering 52w as the Duration? >> >> -- >> Dale A. Howard [MVP] >> VP of Educational Services >> msProjectExperts >> http://www.msprojectexperts.com >> http://www.projectserverexperts.com >> "We write the books on Project Server" >> >> >> "Edward(a)BR" <EdwardBR(a)discussions.microsoft.com> wrote in message >> news:577E64DB-4E8C-4FF6-8B84-599530D917CA(a)microsoft.com... >> > Hi, all >> > >> > How can I insert an one year task duration in Project (time unit 1y >> > don't >> > work)? >> > >> > Thanks >> > ---------------- >> > Edward >>
From: G�rard Ducouret on 1 Apr 2010 14:42 Hi Dale, hi Edward, I think that the "Year" unit was never usable for Duration. It's only usable for resource salary : for exemple John earns $50,000/year. G�rard Ducouret "Dale Howard [MVP]" <dale[dot]howard[at]msprojectexperts[dot]com> a �crit dans le message de news: 30C013CE-3018-4751-A5FF-A3F5EDB6C872(a)microsoft.com... > Edward -- > > When I attempt to enter a Duration value in years, such as "1y" I get a > warning message and the system does not allow me to enter the desired > Duration value. I would suspect it is a bug, but only Microsoft staff > would know for sure. It doesn't work in Project 2010 either, and I don't > know any workaround. Hope this helps. > > -- > Dale A. Howard [MVP] > VP of Educational Services > msProjectExperts > http://www.msprojectexperts.com > http://www.projectserverexperts.com > "We write the books on Project Server" > > > "Edward(a)BR" <EdwardBR(a)discussions.microsoft.com> wrote in message > news:84D4610A-DC67-4882-B77F-395D4A906B5D(a)microsoft.com... >> Hi, Dale >> >> Ok, this is a solution. >> But the question is: why the option at Tools, Options, Edit > View >> options >> for time units in ... ? >> It's really don't works? It's a bug? >> >> Thanks >> ---------------- >> Edward >> >> >> "Dale Howard [MVP]" escreveu: >> >>> Edward -- >>> >>> How about entering 52w as the Duration? >>> >>> -- >>> Dale A. Howard [MVP] >>> VP of Educational Services >>> msProjectExperts >>> http://www.msprojectexperts.com >>> http://www.projectserverexperts.com >>> "We write the books on Project Server" >>> >>> >>> "Edward(a)BR" <EdwardBR(a)discussions.microsoft.com> wrote in message >>> news:577E64DB-4E8C-4FF6-8B84-599530D917CA(a)microsoft.com... >>> > Hi, all >>> > >>> > How can I insert an one year task duration in Project (time unit 1y >>> > don't >>> > work)? >>> > >>> > Thanks >>> > ---------------- >>> > Edward >>>
|