From: "Steve House" sjhouse at hotmail dot on 6 May 2010 08:31 The problem as I see it is grouping by day the work is done rather than by deliverable created. "Day 1" is not s deliverable. "Water Heater Replaced" is. -- Steve House MS Project Trainer & Consultant "whstewart1" <whstewart1.4aj2pb(a)DoNotSpam.com> wrote in message news:whstewart1.4aj2pb(a)DoNotSpam.com... > > Steve- I think you are trying to tell me to do what I have already done. > What was done before I asked the original question which has nothing to > do with any of this. > Here is an example of a particular task. > > Unit1-Day1-Replace Hot Water Heater-Remove Hot Water Heater > > or > > Unit1-Day2-Replace Carpet-Remove Old Carpet > > > I am fixing these apartments up. Rehabbing them for those in the > business. A "phase" in the construction industry as it is every where > else that I know about consists of a variety of tasks not just > "Apartments Painted" > > I have milestones for the end of tasks and for the end of the day or > phase depending on how you like to look at it. > > I don't think that I ever said that DAY1 was my main summary. > > > -- > whstewart1 > ------------------------------------------------------------------------ > whstewart1's Profile: http://forums.techarena.in/members/216370.htm > View this thread: http://forums.techarena.in/microsoft-project/1333215.htm > > http://forums.techarena.in > |