From: JulieS on
Hi Roland,

Are you using Project Server? There may be settings within the
Project Server db that are causing this issue. I am unaware of
any settings specific to Project 2007 without server installed
which may be causing this problem.

You might try re-posting to the server newsgroup on the forums if
you are using Project Server.

see:
http://social.technet.microsoft.com/Forums/en-US/category/projectserver2010,projectprofessional2010

(This newsgroup will be closing on June 1)

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/28/2010 1:44 PM, Roland wrote:
> Hi Julie,
>
> We have an enterprise resource pool but the IMS is being created off the
> server by the macro on a weekly basis. I've manually created the IMS (insert
> project-unlinked) as well and see the same results so I'm wondering if it
> some sort of setting issue(?).
>
> "JulieS" wrote:
>
>> Hi RC,
>>
>> Are you recreating the IMS each time or attempting to add
>> additional data?
>>
>> If you manually consolidate do you see the same issues?
>>
>> I am guessing you have a resource pool or are you attempting to
>> also consolidate the assignments through the macro?
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>> On 5/27/2010 5:51 PM, Roland wrote:
>>> Hi Julie,
>>>
>>> Yes we have SP2 installed. I don't know what the latest installed CU might
>>> be.
>>>
>>> RC
>>>
>>> "JulieS" wrote:
>>>
>>>> Roland,
>>>> I vaguely recall some issues with irregularities showing on work
>>>> in consolidated projects prior to SP-2. Do you have SP-2 installed?
>>>>
>>>> Julie
>>>> Project MVP
>>>>
>>>> Visit http://project.mvps.org/ for the FAQs and additional
>>>> information about Microsoft Project
>>>>
>>>> On 5/25/2010 1:43 PM, Roland wrote:
>>>>> I am using a macro to consolidate multiple schedules into a single IMS. When
>>>>> the macro completed, I noticed about half the resources contained 0 hours in
>>>>> the summary work but contains work on their assigned tasks. MSP identified
>>>>> some resources as being overallocated even with 0 hrs. I am using MSP 2007
>>>>> and Calculation = Automatic.
>>>>>
>>>>> Example:
>>>>>
>>>>> Named Resource 0 hrs (should equal 30)
>>>>> Task 1 10 hrs
>>>>> Task 2 20 hrs
>>>>>
>>>>> Any suggestions as to why some resources work fine but others don't?
>>>>>
>>>> .
>>>>
>> .
>>