Prev: How can I Hide rates in Resource Worksheet
Next: viewing printing report project tells me to adjust margins and sca
From: Roland on 25 May 2010 13:43 I am using a macro to consolidate multiple schedules into a single IMS. When the macro completed, I noticed about half the resources contained 0 hours in the summary work but contains work on their assigned tasks. MSP identified some resources as being overallocated even with 0 hrs. I am using MSP 2007 and Calculation = Automatic. Example: Named Resource 0 hrs (should equal 30) Task 1 10 hrs Task 2 20 hrs Any suggestions as to why some resources work fine but others don't?
From: JulieS on 25 May 2010 14:47 Roland, I vaguely recall some issues with irregularities showing on work in consolidated projects prior to SP-2. Do you have SP-2 installed? Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/25/2010 1:43 PM, Roland wrote: > I am using a macro to consolidate multiple schedules into a single IMS. When > the macro completed, I noticed about half the resources contained 0 hours in > the summary work but contains work on their assigned tasks. MSP identified > some resources as being overallocated even with 0 hrs. I am using MSP 2007 > and Calculation = Automatic. > > Example: > > Named Resource 0 hrs (should equal 30) > Task 1 10 hrs > Task 2 20 hrs > > Any suggestions as to why some resources work fine but others don't? >
From: Roland on 27 May 2010 17:51 Hi Julie, Yes we have SP2 installed. I don't know what the latest installed CU might be. RC "JulieS" wrote: > Roland, > I vaguely recall some issues with irregularities showing on work > in consolidated projects prior to SP-2. Do you have SP-2 installed? > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional > information about Microsoft Project > > On 5/25/2010 1:43 PM, Roland wrote: > > I am using a macro to consolidate multiple schedules into a single IMS. When > > the macro completed, I noticed about half the resources contained 0 hours in > > the summary work but contains work on their assigned tasks. MSP identified > > some resources as being overallocated even with 0 hrs. I am using MSP 2007 > > and Calculation = Automatic. > > > > Example: > > > > Named Resource 0 hrs (should equal 30) > > Task 1 10 hrs > > Task 2 20 hrs > > > > Any suggestions as to why some resources work fine but others don't? > > > . >
From: JulieS on 27 May 2010 19:42 Hi RC, Are you recreating the IMS each time or attempting to add additional data? If you manually consolidate do you see the same issues? I am guessing you have a resource pool or are you attempting to also consolidate the assignments through the macro? Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/27/2010 5:51 PM, Roland wrote: > Hi Julie, > > Yes we have SP2 installed. I don't know what the latest installed CU might > be. > > RC > > "JulieS" wrote: > >> Roland, >> I vaguely recall some issues with irregularities showing on work >> in consolidated projects prior to SP-2. Do you have SP-2 installed? >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information about Microsoft Project >> >> On 5/25/2010 1:43 PM, Roland wrote: >>> I am using a macro to consolidate multiple schedules into a single IMS. When >>> the macro completed, I noticed about half the resources contained 0 hours in >>> the summary work but contains work on their assigned tasks. MSP identified >>> some resources as being overallocated even with 0 hrs. I am using MSP 2007 >>> and Calculation = Automatic. >>> >>> Example: >>> >>> Named Resource 0 hrs (should equal 30) >>> Task 1 10 hrs >>> Task 2 20 hrs >>> >>> Any suggestions as to why some resources work fine but others don't? >>> >> . >>
From: Roland on 28 May 2010 13:44
Hi Julie, We have an enterprise resource pool but the IMS is being created off the server by the macro on a weekly basis. I've manually created the IMS (insert project-unlinked) as well and see the same results so I'm wondering if it some sort of setting issue(?). "JulieS" wrote: > Hi RC, > > Are you recreating the IMS each time or attempting to add > additional data? > > If you manually consolidate do you see the same issues? > > I am guessing you have a resource pool or are you attempting to > also consolidate the assignments through the macro? > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional > information about Microsoft Project > > On 5/27/2010 5:51 PM, Roland wrote: > > Hi Julie, > > > > Yes we have SP2 installed. I don't know what the latest installed CU might > > be. > > > > RC > > > > "JulieS" wrote: > > > >> Roland, > >> I vaguely recall some issues with irregularities showing on work > >> in consolidated projects prior to SP-2. Do you have SP-2 installed? > >> > >> Julie > >> Project MVP > >> > >> Visit http://project.mvps.org/ for the FAQs and additional > >> information about Microsoft Project > >> > >> On 5/25/2010 1:43 PM, Roland wrote: > >>> I am using a macro to consolidate multiple schedules into a single IMS. When > >>> the macro completed, I noticed about half the resources contained 0 hours in > >>> the summary work but contains work on their assigned tasks. MSP identified > >>> some resources as being overallocated even with 0 hrs. I am using MSP 2007 > >>> and Calculation = Automatic. > >>> > >>> Example: > >>> > >>> Named Resource 0 hrs (should equal 30) > >>> Task 1 10 hrs > >>> Task 2 20 hrs > >>> > >>> Any suggestions as to why some resources work fine but others don't? > >>> > >> . > >> > . > |