From: Dale Howard [MVP] on
Steve --

Thanks for your excellent clarification! :)

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Steve House" <sjhouse at hotmail dot com> wrote in message
news:e7Q$Z8JvKHA.5940(a)TK2MSFTNGP02.phx.gbl...
> Note that chqanging the "hours per day" field on the Tools/Options menu,
> Calendar page DOES NOT affect the calculations where the hours worked per
> day enter in. This field is actually a conversion factor, used by Project
> to convert a duration entered in the units of "Days" or "Weeks" into units
> of hours, hence minutes, for storage in the task database. To change the
> hours per day that the resource works such as is used in the equation Dale
> cites, you must modify the calendar workday using the Tools,
> ChangeWorkingTime menu option. The Calendar Options page does not affecgt
> that.
> --
> Steve House
> MS Project Trainer & Consultant
>
>
> "TBol" <TBol(a)discussions.microsoft.com> wrote in message
> news:F0AA5024-434B-4262-8371-86ED35C96BAB(a)microsoft.com...
>> Thanks Dale. Sorry, I did not explain well. I've changed "Hours per day"
>> setting into 9 hours on Calendar tab of the Options DB. My task duration
>> is 3
>> x 9 = 27 hours and
>> I need 27 person-hours to complete the task. On the other hand, resource
>> has
>> 8 hours per day. Project will spread the resource hours as 8,8,8,3. I am
>> fine with all that.
>>
>> The formula is (single task - single resource) as follows:
>> Work = Task Duration x (Resource Hours Per Day x Units).
>>
>> What I don't understand is that if we build the work formula based on the
>> working hours of resource (which is 8 hours per day) how can we get 27
>> person-hours out of "Work = Duration * Units" calculation.
>>
>> "Dale Howard [MVP]" wrote:
>>
>>> TBol --
>>>
>>> To be technically correct, the Duration Equation formula is written as:
>>>
>>> Duration = Work/(Hours Per Day x Units)
>>>
>>> You find the Hours Per Day value on the Calendar page of the Options
>>> dialog,
>>> accessed by clicking Tools - Options - Calendar. You were missing one
>>> key
>>> part of the formula, which is the Hours Per Day value. Hope this helps.
>>>
>>> --
>>> Dale A. Howard [MVP]
>>> VP of Educational Services
>>> msProjectExperts
>>> http://www.msprojectexperts.com
>>> http://www.projectserverexperts.com
>>> "We write the books on Project Server"
>>>
>>>
>>> "TBol" <TBol(a)discussions.microsoft.com> wrote in message
>>> news:2C6FDDC6-0416-4AB4-81AC-5296328BE166(a)microsoft.com...
>>> > I know both are the same equation. Which one is by definition ?
>>> > "Duration
>>> > =
>>> > Work / Units" or "Work = Duration x Units".
>>> > I have a three day task with a resource assigned (Max. Units 100%,
>>> > Units:100%). All calendars are the default Standard base calendar;
>>> > Hours
>>> > per
>>> > day is 9 hours. How do we build the equation to calculate 27 hours of
>>> > work
>>> > ?
>>> >
>>> >
>>> >
>
First  |  Prev  | 
Pages: 1 2 3
Prev: Formulas/custom field
Next: Resource Leveling - Cash