From: TBol on
I know both are the same equation. Which one is by definition ? "Duration =
Work / Units" or "Work = Duration x Units".
I have a three day task with a resource assigned (Max. Units 100%,
Units:100%). All calendars are the default Standard base calendar; Hours per
day is 9 hours. How do we build the equation to calculate 27 hours of work ?



From: Dale Howard [MVP] on
TBol --

To be technically correct, the Duration Equation formula is written as:

Duration = Work/(Hours Per Day x Units)

You find the Hours Per Day value on the Calendar page of the Options dialog,
accessed by clicking Tools - Options - Calendar. You were missing one key
part of the formula, which is the Hours Per Day value. Hope this helps.

--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"TBol" <TBol(a)discussions.microsoft.com> wrote in message
news:2C6FDDC6-0416-4AB4-81AC-5296328BE166(a)microsoft.com...
> I know both are the same equation. Which one is by definition ? "Duration
> =
> Work / Units" or "Work = Duration x Units".
> I have a three day task with a resource assigned (Max. Units 100%,
> Units:100%). All calendars are the default Standard base calendar; Hours
> per
> day is 9 hours. How do we build the equation to calculate 27 hours of work
> ?
>
>
>
From: Andrew Lavinsky on

Most people use D = U X W, which means W = D/U

It's really D = (U X PHPD) X W, where PHPD = Person Hours Per Day.

Then just pick which variable to solve for.


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

> I know both are the same equation. Which one is by definition ?
> "Duration =
> Work / Units" or "Work = Duration x Units".
> I have a three day task with a resource assigned (Max. Units 100%,
> Units:100%). All calendars are the default Standard base calendar;
> Hours per
> day is 9 hours. How do we build the equation to calculate 27 hours of
> work ?


From: Andrew Lavinsky on
My bad. Please belay that last note, let's try it again:

D X U = W, should really be D X (U X PHPD) = W, with PHPD = Person Hours
Per Day.

Then solve for the correct variable.


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

> I know both are the same equation. Which one is by definition ?
> "Duration =
> Work / Units" or "Work = Duration x Units".
> I have a three day task with a resource assigned (Max. Units 100%,
> Units:100%). All calendars are the default Standard base calendar;
> Hours per
> day is 9 hours. How do we build the equation to calculate 27 hours of
> work ?


From: TBol on
Thanks Dale. Sorry, I did not explain well. I've changed "Hours per day"
setting into 9 hours on Calendar tab of the Options DB. My task duration is 3
x 9 = 27 hours and
I need 27 person-hours to complete the task. On the other hand, resource has
8 hours per day. Project will spread the resource hours as 8,8,8,3. I am
fine with all that.

The formula is (single task - single resource) as follows:
Work = Task Duration x (Resource Hours Per Day x Units).

What I don't understand is that if we build the work formula based on the
working hours of resource (which is 8 hours per day) how can we get 27
person-hours out of "Work = Duration * Units" calculation.

"Dale Howard [MVP]" wrote:

> TBol --
>
> To be technically correct, the Duration Equation formula is written as:
>
> Duration = Work/(Hours Per Day x Units)
>
> You find the Hours Per Day value on the Calendar page of the Options dialog,
> accessed by clicking Tools - Options - Calendar. You were missing one key
> part of the formula, which is the Hours Per Day value. Hope this helps.
>
> --
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
>
>
> "TBol" <TBol(a)discussions.microsoft.com> wrote in message
> news:2C6FDDC6-0416-4AB4-81AC-5296328BE166(a)microsoft.com...
> > I know both are the same equation. Which one is by definition ? "Duration
> > =
> > Work / Units" or "Work = Duration x Units".
> > I have a three day task with a resource assigned (Max. Units 100%,
> > Units:100%). All calendars are the default Standard base calendar; Hours
> > per
> > day is 9 hours. How do we build the equation to calculate 27 hours of work
> > ?
> >
> >
> >
 |  Next  |  Last
Pages: 1 2 3
Prev: Formulas/custom field
Next: Resource Leveling - Cash