From: Barbara - Austria on
Hi Az.,

Are you resources 'organized' in groups?

Group X Shift - A in January
Group X Shift - B in February
Group X Shift - C in March

Group Y Shift - B in January
Group Y Shift - C in February
Group Y Shift - A in March

…..

If you have that situation you could create a calendar for each group. In
these calendar you need to use Tab 'Work Weeks'. Create a line for each month
with Start and Finish and enter your working time in Details… It is some work
more in the beginning, one line for each month in three calendars…. But you
will not need to change resource calendars each month and your schedules will
not be messed up.

Does that help?
Regards
Barbara


"Az." wrote:

>
> Hi;
>
> Resources in the organization work in 3 shifts and their ROTA is set on
> monthly basis. At this moment, I am changing their workign time on monthly
> basis for the shift that they've been assigned to. This takes up
> considerable time.
>
> Although I can create three shift calendars and assign them to appropriate
> resources - but is there a way where I can assign time-bound shift calendars
> to a resource in a way that it doesn't mess up my project schedule. Let me
> illustrate with an example
>
> Shift - A 9AM-5PM
> Shift - B 5PM-1AM
> Shift - C 1AM-9AM
>
> Resorce - 1 Shift - A in January
> Resource - 1 Shift - B in February
> Resource - 1 Shift - C in March
>
> Shifts do not change, but resources do. Is there a way I can assign shift A
> to resource 1 for january and then shft B for february so on ...
>
>
> Thanks
> Az.
>
From: Barbara - Austria on
Hi Az.,

sorry, I think my description was misleading since I have tested before
writing the post. I will give it another try.

What I wanted to tell: if there are e.g. 3 groups with their shift rhythm,
you could create one calendar for each of these groups (calendar X for
members of group X, calendar Y for members of group Y, calendar Z for members
of group Z).
For each of these calendars define the appropriate shift hours for each month.
Assign one of these calendars to your resources.
Make sure that your project calendar allows working 24hrs a day.

If you want to, you can give me your e-mail address, so I can send my example.

Regards
Barbara

"Az." wrote:

> Unfortunately they don't work in 'groups' as u sggested. :-(
>
> --
> Thank you
> Az.
>
>
> "Az." wrote:
>
> > Hi Barbara
> >
> > Thanks for your response. Will try it and let u know.
> >
> > --
> > Thank you
> > Az.
> >
> >
> > "Barbara - Austria" wrote:
> >
> > > Hi Az.,
> > >
> > > Are you resources 'organized' in groups?
> > >
> > > Group X Shift - A in January
> > > Group X Shift - B in February
> > > Group X Shift - C in March
> > >
> > > Group Y Shift - B in January
> > > Group Y Shift - C in February
> > > Group Y Shift - A in March
> > >
> > > …..
> > >
> > > If you have that situation you could create a calendar for each group. In
> > > these calendar you need to use Tab 'Work Weeks'. Create a line for each month
> > > with Start and Finish and enter your working time in Details… It is some work
> > > more in the beginning, one line for each month in three calendars…. But you
> > > will not need to change resource calendars each month and your schedules will
> > > not be messed up.
> > >
> > > Does that help?
> > > Regards
> > > Barbara
> > >
> > >
> > > "Az." wrote:
> > >
> > > >
> > > > Hi;
> > > >
> > > > Resources in the organization work in 3 shifts and their ROTA is set on
> > > > monthly basis. At this moment, I am changing their workign time on monthly
> > > > basis for the shift that they've been assigned to. This takes up
> > > > considerable time.
> > > >
> > > > Although I can create three shift calendars and assign them to appropriate
> > > > resources - but is there a way where I can assign time-bound shift calendars
> > > > to a resource in a way that it doesn't mess up my project schedule. Let me
> > > > illustrate with an example
> > > >
> > > > Shift - A 9AM-5PM
> > > > Shift - B 5PM-1AM
> > > > Shift - C 1AM-9AM
> > > >
> > > > Resorce - 1 Shift - A in January
> > > > Resource - 1 Shift - B in February
> > > > Resource - 1 Shift - C in March
> > > >
> > > > Shifts do not change, but resources do. Is there a way I can assign shift A
> > > > to resource 1 for january and then shft B for february so on ...
> > > >
> > > >
> > > > Thanks
> > > > Az.
> > > >