From: mrobles on 11 Feb 2010 20:00 I have tasks that started and finished in the past. In addition, I have manually marked them as completed. Why are they still showing up in my Unstarted Tasks report?
From: Trevor Rabey on 11 Feb 2010 21:37
The unstarted tasks report just uses the unstarted tasks filter to find tasks where Actual Start = NA. Check the filter (Project, Filtered For, More Filters etc). Check the Actual Start field in the Tracking Table. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "mrobles" <mrobles(a)discussions.microsoft.com> wrote in message news:3E9D4C4F-B764-47DC-BDA4-3CA8F4E8A395(a)microsoft.com... >I have tasks that started and finished in the past. In addition, I have > manually marked them as completed. Why are they still showing up in my > Unstarted Tasks report? |