From: mrobles on
I have tasks that started and finished in the past. In addition, I have
manually marked them as completed. Why are they still showing up in my
Unstarted Tasks report?
From: Trevor Rabey on
The unstarted tasks report just uses the unstarted tasks filter to find
tasks where Actual Start = NA.
Check the filter (Project, Filtered For, More Filters etc).
Check the Actual Start field in the Tracking Table.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au