From: Maanu on
Hi,

I would like to start a task two days after starting another task.

Is that possibloe?

Thanks!
From: Jan De Messemaeker on

Hi,

You can make a task start AT LEAST 2 days after an other task
Double-Click on the successor tasks's row (any cell will do) and in the
predecessor's column, select the predecessor's name or ID, type= Start to
Start, Lag=2d.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Maanu" <Maanu(a)discussions.microsoft.com> wrote in message
news:7D9FD0DF-70C2-4408-8CA8-C2537140B227(a)microsoft.com...
> Hi,
>
> I would like to start a task two days after starting another task.
>
> Is that possibloe?
>
> Thanks!


From: John on
In article <7D9FD0DF-70C2-4408-8CA8-C2537140B227(a)microsoft.com>,
Maanu <Maanu(a)discussions.microsoft.com> wrote:

> Hi,
>
> I would like to start a task two days after starting another task.
>
> Is that possibloe?
>
> Thanks!

Maau,
Yes, the simplest structure is with a lag in the task's predecessor. For
example, if you want task 11 to start 2 working days after task 10, the
the Predecessor for task 11 should be:
10SS+2d

If you want calendar days instead of working days, then use:
10SS+2ed

John
Project MVP
From: Trevor Rabey on
Not quite.
What you can do is say that the successor task cannot start any earlier than
2 days after the predecessor task starts.
It may seem a trial distinction but it can make all the difference in the
world.
Double click the successor for Task Information, Predecessors, and set the
predecessor to SS+2d.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Maanu" <Maanu(a)discussions.microsoft.com> wrote in message
news:7D9FD0DF-70C2-4408-8CA8-C2537140B227(a)microsoft.com...
> Hi,
>
> I would like to start a task two days after starting another task.
>
> Is that possibloe?
>
> Thanks!