From: "Steve House" sjhouse at hotmail dot on
A task type of Fixed Duration DOES NOT mean that the duration is engraved in
granite and will never change under any circumstance, nor does it mean it's
read-only and cannot be edited. It means that when you have a resource
assigned and edit one of the assignment parameters so as to change either
the work performed by the resource or the effort units he's assigned to
work, the duration will remain constant and the either the units will change
(when editing work) or the work will change (when editing units).

"Sumit" <Sumit(a)discussions.microsoft.com> wrote in message
news:9BB0D95C-AD65-42AB-B08C-FD08FAD9AE3C(a)microsoft.com...
> Hi...
>
> I have tasks with task type as fixed duration.
>
> While importing data for assignments for that task I notice that the
> DURATION gets AUTOMATICALLY changed in 2 cases:-
>
> 1) When I am importing actual effort for assignment
> or
> 2) When I import actual start date for that assignment( assignment doesn't
> have actual finish date as of now).
>
> I am not able to find the logic why MSP is doing that.
>
> Any help or insight into the behavior is really appreciated!!
>
> Thanks a lot in advance!!!
>
> --
> --Sumit