From: Tom Mc on
Thanks Jon. You are essentially confirming what was becoming evident with
Deltek - that there is no product development nor fixes for current issues,
particularly with MSP 2007. I ask a Risk+ tech support person about any
plans for collaborating with Microsoft and fixing the MSP 2007 compatibility
issue and he said "no". Our only near term solution appears to be to keep a
copy of MSP 2003 going.

"Jon M. Kelley" wrote:

> We had been warned by our in house testers that Ms Project 2007 and Risk+
> didn't appear to be completely compatible (extended run times, random errors,
> program hanging forever). When our corporation moved to office 2007, a small
> group of schedulers and engineers kept Ms Project 2003 instead of moving to
> 2007. On a monthly basis, we run Risk+ simulations on relatively large
> schedules (7,000 to 10,000 tasks), with 2,000 to 4,000 iterations. These
> runs take 2 to 8 hours on a multiprocessor HP engineering workstation, and
> are consistent enough that the time variations between runs of a given
> schedule is less than five percent, depending primarily on what else is
> running during the Risk+ simulation. Our simulation runs are primarily done
> to generate S-Curves & completion confidence intervals for particular tasks.
> Things that we've found that cause a large jump in run time is to include
> “Duration Analysis”, Cost Analysis”, “Critical Path Analysis”, and
> “Sensitivity Analysis”.
>
> My own history with Risk+ started before Deltek acquired the product from CS
> Solutions. I tried working with the CS Solutions programming team assigned
> to support Risk+. What I was eventually told by the team lead was that when
> CS Solutions acquired the product from ProjectGear Inc, they got the source
> code, with little knowledge of how or why it worked, and as long as the
> product sold, weren't willing to even work on known bugs. When Deltek
> acquired the product, we still had maintenance contracts, and tried again to
> work with the Deltek developers, with the same result – about the only change
> they were willing to make was to replace “CS Solutions” name in the product
> with “Deltek Systems”.
>
> The current drive at our corporate level is to move to Oracle Primavera, but
> with our customers are still requesting Ms Project 2003 schedules with Risk+
> analysis, we have to convince our customers that Oracle will provide better
> long term support than Deltek has provided.
>
>
> "Tom Mc" wrote:
>
> > I tried a test as follows:
> > I created a brand new file from scratch. Added 200 tasks - each of 20 days
> > duration. Linked them all as one long sequence. Added basic risk loading -
> > i.e., "initialized most likely", then "quick setup". I set the calc method
> > to "manual". Thus, I now have a very small and simplistic file (no formulas,
> > no custom fields, no baselines, etc., etc.). It STILL took 20 minutes for
> > 1000 samples.
> >
> > BTW... I spoke to Risk+ tech spt. They were unable to give me any
> > worthwhile advice - except to "talk to Microsoft". I really don't want to
> > pay money to get an answer.
> >
> > Thoughts?
> >
> > "AnthemAZ" wrote:
> >
> > > Tom Mc
> > >
> > > Can you share your file? I'd like to look deeper for you as I've used R+
> > > for many years and there are some tests I can run to isolate the performance.
> > >
> > > I'm using MSP 03. If available, sent to wjordan(a)gdc4s.com
> > >
> > >
> > >
> > >
> > > "Tom Mc" wrote:
> > >
> > > > Thanks for a good suggestion. However, it didn't seem to make a difference
> > > > when I disabled all the custom field formulas. It still took about 20
> > > > minutes for 1000 samples of a small file (only 153 tasks).
> > > >
> > > > "AnthemAZ" wrote:
> > > >
> > > > > Tom Mc
> > > > >
> > > > > Check your file(s) for any custom fields with a formula. Remove them and
> > > > > you should see an improvement in perf.
> > > > >
> > > > > This will slow R+ significantly when running simulations.
> > > > >
> > > > > AnthemAz
> > > > >
> > > > > "Rob Schneider" wrote:
> > > > >
> > > > > > I'd be curious to hear what the Risk+ people say on this?
> > > > > >
> > > > > >
> > > > > > --rms
> > > > > >
> > > > > > www.rmschneider.com
> > > > > >
> > > > > >
> > > > > >
> > > > > >
> > > > > > On 04/03/10 18:37, Tom Mc wrote:
> > > > > > > I have tried on several instances with seveal machines and several files a
> > > > > > > consistent and significant performance problem with P2007. For example, I
> > > > > > > have a small file with only 153 tasks and it takes 20 minutes to run 1000
> > > > > > > samples. I have found that other people have had similar performance
> > > > > > > problems with P2007.
> > > > > > >
> > > > > > > I run the simulation on a file stored on my desktop (local), so network
> > > > > > > latency is not an issue.
> > > > > > >
> > > > > > > Any other thoughts? Thanks - Tom
> > > > > > >
> > > > > > > "Jim Aksel" wrote:
> > > > > > >
> > > > > > >> We use Risk+ quite frequently in P2003, P2007 and P2010. There is no
> > > > > > >> appreciable difference in performance between the patforms.
> > > > > > >>
> > > > > > >> Might you have files accessed externally from a shared server? We did find
> > > > > > >> network latency to be a problem on Master Projects stored out on the servers.
> > > > > > >> --
> > > > > > >> If this post was helpful, please consider rating it.
> > > > > > >>
> > > > > > >> Jim Aksel, MVP
> > > > > > >>
> > > > > > >> Check out my blog for more information:
> > > > > > >> http://www.msprojectblog.com
> > > > > > >>
> > > > > > >>
> > > > > > >>
> > > > > > >> "Tom Mc" wrote:
> > > > > > >>
> > > > > > >>> We use Risk+ as a risk simulation tool. We have discovered that it works
> > > > > > >>> approximately 20 times SLOWER in MSP 2007 than MSP 2003. Has anyone else run
> > > > > > >>> into this problem. If so, is there a remedy?
> > > > > > .
> > > > > >