Prev: Resource Loading
Next: Project 2007
From: jackie on 10 Mar 2010 18:53 Hello I would like to find out what is the most efficient way to check the status of the predecessors of any tasks in the plan I have a plan with a large number of tasks and for instance task 540, has 10 predecessors each at different stages of completion scattered throughout the plan. Currently if I want to know how each predecessor is progressing I need to locate the predecessor manually, and I would be grateful for some advice on how to do this more efficiently Many thanks J
From: Trevor Rabey on 10 Mar 2010 21:36 Use a flag field (Flag1), flag the tasks you are interested in (540 and all of its predecessors), then make a filter which returns all flagged tasks. Its quick and drty and it works. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "jackie" <jackie(a)discussions.microsoft.com> wrote in message news:58760F73-5608-4B15-BD1C-9224D5BCCE56(a)microsoft.com... > Hello > > I would like to find out what is the most efficient way to check the > status > of the predecessors of any tasks in the plan > > I have a plan with a large number of tasks and for instance task 540, has > 10 > predecessors each at different stages of completion scattered throughout > the > plan. Currently if I want to know how each predecessor is progressing I > need > to locate the predecessor manually, and I would be grateful for some > advice > on how to do this more efficiently > > Many thanks > J
From: Jim Aksel on 10 Mar 2010 23:06 Generally this question is really asking "What is driving the start date of this task." In Project 2007 and later, there is a featue called "What's driving my task". Although it does not give you specific %Complete, it will provide needed information. In addition to Trevor's excellent (and inexpensive) solution, a coded solution is also possible. This is not freeware, but is available. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "jackie" wrote: > Hello > > I would like to find out what is the most efficient way to check the status > of the predecessors of any tasks in the plan > > I have a plan with a large number of tasks and for instance task 540, has 10 > predecessors each at different stages of completion scattered throughout the > plan. Currently if I want to know how each predecessor is progressing I need > to locate the predecessor manually, and I would be grateful for some advice > on how to do this more efficiently > > Many thanks > J
From: Jack Dahlgren MVP on 11 Mar 2010 12:34 There is a freeware solution - my trace macro. Select the task, run the macro and it will filter the project to show the predecessors. You can find it here: http://masamiki.com/project/macros.htm -Jack "Jim Aksel" <JimAksel(a)discussions.microsoft.com> wrote in message news:039C2D0C-B6B3-4819-AC36-9ED11827A429(a)microsoft.com... > Generally this question is really asking "What is driving the start date > of > this task." In Project 2007 and later, there is a featue called "What's > driving my task". Although it does not give you specific %Complete, it > will > provide needed information. > > In addition to Trevor's excellent (and inexpensive) solution, a coded > solution is also possible. This is not freeware, but is available. > -- > If this post was helpful, please consider rating it. > > Jim Aksel, MVP > > Check out my blog for more information: > http://www.msprojectblog.com > > > > "jackie" wrote: > >> Hello >> >> I would like to find out what is the most efficient way to check the >> status >> of the predecessors of any tasks in the plan >> >> I have a plan with a large number of tasks and for instance task 540, has >> 10 >> predecessors each at different stages of completion scattered throughout >> the >> plan. Currently if I want to know how each predecessor is progressing I >> need >> to locate the predecessor manually, and I would be grateful for some >> advice >> on how to do this more efficiently >> >> Many thanks >> J
|
Pages: 1 Prev: Resource Loading Next: Project 2007 |