From: Shahriar Nour Khondokar on 8 Apr 2010 01:45 Thanks Barbara and Andrew for your replies. I have done some experimenting of my own and found a way of doing this different from what is described above. I created a fixed work task and assigned a 100% resource to it. The duration is calculated automatically. Now, if i add 'e' to the duration, it schedules the task during non working hours. Hence I did not have to create or use a 24hrs calendar specifically for this task. Can someone please confirm that it is OK to follow this approach? Thanks http://www.shahriarnk.com/ "Andrew Lavinsky" wrote: > The task would need to be set to a 24 hour calendar, with the resources assigned > as well - or the task is set to ignore resource calendars. > > - Andrew Lavinsky > Blog: http://blogs.catapultsystems.com/epm > > > Hi > > my duration is actually being calculated by MS Project based on the > > value I > > enter for Work and Resource availability %; i.e. I dont enter any > > value for > > duration. > > But i still want the work to occur during non-working time using > > elapsed duration. > > > > Is this possible? If so how? > > > > "Barbara - Austria" wrote: > > > >> Hi, > >> > >> does entering 7 edays (instead of 7 days) not what you want it to do? > >> It is working for fixed-work tasks also. > >> > >> Regards > >> Barbara > >> "Shahriar Nour Khondokar" > >> <ShahriarNourKhondokar(a)discussions.microsoft.com> schrieb im > >> Newsbeitrag > >> news:78DDD217-3CE6-4E2D-A774-E2D03ED8A7D0(a)microsoft.com... > >> > >>> HI.. > >>> is it possible to have a fixed-work task scheduled over elapsed > >>> duration? > >>> In other words, i have a fixed-work task which I want to occur in > >>> non-working time too; i.e. after 5PM in the Standard Calendar. > >>> > >>> Please let me how to accomplish this. > >>> > >>> Thanks > >>> > > > . >
From: Barbara - Austria on 8 Apr 2010 01:53
Hi, this appraoch is fine (and was in fact my first suggestion ;-)). Since I understood from your earlier post that you didn't want to edit duration, I described a possibilty without doing that. And so did Andrew. Regards Barbara "Shahriar Nour Khondokar" <ShahriarNourKhondokar(a)discussions.microsoft.com> schrieb im Newsbeitrag news:C8DDA7FC-3F82-454F-9A0D-2BC791DBFC4B(a)microsoft.com... > Thanks Barbara and Andrew for your replies. > I have done some experimenting of my own and found a way of doing this > different from what is described above. > > I created a fixed work task and assigned a 100% resource to it. > > The duration is calculated automatically. > > Now, if i add 'e' to the duration, it schedules the task during non > working > hours. Hence I did not have to create or use a 24hrs calendar specifically > for this task. > > Can someone please confirm that it is OK to follow this approach? > > Thanks > http://www.shahriarnk.com/ > > "Andrew Lavinsky" wrote: > >> The task would need to be set to a 24 hour calendar, with the resources >> assigned >> as well - or the task is set to ignore resource calendars. >> >> - Andrew Lavinsky >> Blog: http://blogs.catapultsystems.com/epm >> >> > Hi >> > my duration is actually being calculated by MS Project based on the >> > value I >> > enter for Work and Resource availability %; i.e. I dont enter any >> > value for >> > duration. >> > But i still want the work to occur during non-working time using >> > elapsed duration. >> > >> > Is this possible? If so how? >> > >> > "Barbara - Austria" wrote: >> > >> >> Hi, >> >> >> >> does entering 7 edays (instead of 7 days) not what you want it to do? >> >> It is working for fixed-work tasks also. >> >> >> >> Regards >> >> Barbara >> >> "Shahriar Nour Khondokar" >> >> <ShahriarNourKhondokar(a)discussions.microsoft.com> schrieb im >> >> Newsbeitrag >> >> news:78DDD217-3CE6-4E2D-A774-E2D03ED8A7D0(a)microsoft.com... >> >> >> >>> HI.. >> >>> is it possible to have a fixed-work task scheduled over elapsed >> >>> duration? >> >>> In other words, i have a fixed-work task which I want to occur in >> >>> non-working time too; i.e. after 5PM in the Standard Calendar. >> >>> >> >>> Please let me how to accomplish this. >> >>> >> >>> Thanks >> >>> >> >> >> . >> |