From: Shahriar Nour Khondokar on
HI..
is it possible to have a fixed-work task scheduled over elapsed duration?

In other words, i have a fixed-work task which I want to occur in
non-working time too; i.e. after 5PM in the Standard Calendar.

Please let me how to accomplish this.

Thanks
From: Barbara - Austria on
Hi,

does entering 7 edays (instead of 7 days) not what you want it to do? It is
working for fixed-work tasks also.

Regards
Barbara

"Shahriar Nour Khondokar" <ShahriarNourKhondokar(a)discussions.microsoft.com>
schrieb im Newsbeitrag
news:78DDD217-3CE6-4E2D-A774-E2D03ED8A7D0(a)microsoft.com...
> HI..
> is it possible to have a fixed-work task scheduled over elapsed duration?
>
> In other words, i have a fixed-work task which I want to occur in
> non-working time too; i.e. after 5PM in the Standard Calendar.
>
> Please let me how to accomplish this.
>
> Thanks

From: Shahriar Nour Khondokar on
Hi
my duration is actually being calculated by MS Project based on the value I
enter for Work and Resource availability %; i.e. I dont enter any value for
duration.

But i still want the work to occur during non-working time using elapsed
duration.

Is this possible? If so how?

"Barbara - Austria" wrote:

> Hi,
>
> does entering 7 edays (instead of 7 days) not what you want it to do? It is
> working for fixed-work tasks also.
>
> Regards
> Barbara
>
> "Shahriar Nour Khondokar" <ShahriarNourKhondokar(a)discussions.microsoft.com>
> schrieb im Newsbeitrag
> news:78DDD217-3CE6-4E2D-A774-E2D03ED8A7D0(a)microsoft.com...
> > HI..
> > is it possible to have a fixed-work task scheduled over elapsed duration?
> >
> > In other words, i have a fixed-work task which I want to occur in
> > non-working time too; i.e. after 5PM in the Standard Calendar.
> >
> > Please let me how to accomplish this.
> >
> > Thanks
>
From: Barbara - Austria on
Hi,

now I got it (at least I think so).

First you need a second calendar:
Tools - Change Working Time ...Create New Calendar. Create a new one, if you
don't need any holidays. Go to tab 'Work Weeks', mark [Default] and click on
Details.... Change working times for the days you want to perform your
tasks. Finish with OK.

Open Task Information, select your new calendar and enable 'Scheduling
ignores resource calendars' on tab 'Advanced'.

If you have questions let me know!
Regards
Barbara


"Shahriar Nour Khondokar" <ShahriarNourKhondokar(a)discussions.microsoft.com>
schrieb im Newsbeitrag
news:9A80C7CA-A6E8-47F3-8EB0-8FD0C4730F88(a)microsoft.com...
> Hi
> my duration is actually being calculated by MS Project based on the value
> I
> enter for Work and Resource availability %; i.e. I dont enter any value
> for
> duration.
>
> But i still want the work to occur during non-working time using elapsed
> duration.
>
> Is this possible? If so how?
>
> "Barbara - Austria" wrote:
>
>> Hi,
>>
>> does entering 7 edays (instead of 7 days) not what you want it to do? It
>> is
>> working for fixed-work tasks also.
>>
>> Regards
>> Barbara
>>
>> "Shahriar Nour Khondokar"
>> <ShahriarNourKhondokar(a)discussions.microsoft.com>
>> schrieb im Newsbeitrag
>> news:78DDD217-3CE6-4E2D-A774-E2D03ED8A7D0(a)microsoft.com...
>> > HI..
>> > is it possible to have a fixed-work task scheduled over elapsed
>> > duration?
>> >
>> > In other words, i have a fixed-work task which I want to occur in
>> > non-working time too; i.e. after 5PM in the Standard Calendar.
>> >
>> > Please let me how to accomplish this.
>> >
>> > Thanks
>>

From: Andrew Lavinsky on
The task would need to be set to a 24 hour calendar, with the resources assigned
as well - or the task is set to ignore resource calendars.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

> Hi
> my duration is actually being calculated by MS Project based on the
> value I
> enter for Work and Resource availability %; i.e. I dont enter any
> value for
> duration.
> But i still want the work to occur during non-working time using
> elapsed duration.
>
> Is this possible? If so how?
>
> "Barbara - Austria" wrote:
>
>> Hi,
>>
>> does entering 7 edays (instead of 7 days) not what you want it to do?
>> It is working for fixed-work tasks also.
>>
>> Regards
>> Barbara
>> "Shahriar Nour Khondokar"
>> <ShahriarNourKhondokar(a)discussions.microsoft.com> schrieb im
>> Newsbeitrag
>> news:78DDD217-3CE6-4E2D-A774-E2D03ED8A7D0(a)microsoft.com...
>>
>>> HI..
>>> is it possible to have a fixed-work task scheduled over elapsed
>>> duration?
>>> In other words, i have a fixed-work task which I want to occur in
>>> non-working time too; i.e. after 5PM in the Standard Calendar.
>>>
>>> Please let me how to accomplish this.
>>>
>>> Thanks
>>>