From: alm80 on
Hello,
I need to change the working week to start on Sunday, and end on Thursday,
so that Friday and Saturday are days off. When I change this in "Change
Working Time", this has no effect on the calendar itself. I see
Saturdays/Sundays as days off. Is there any way to change also the visual
settings of the calendar to reflect this change. I can set those manually
with non-standard working time, etc. But it's a lot of work for multi-month
projects. I'd like this option to be set as default.
From: HansH on
Using "Change Working Time", you can specify the work week you need
(Friday = non-working and Sunday = specific working times).
To visually show these changes in the Gantt Chart, right-click the Gantt
Chart and select Non-Working Time. You can specify the calendar to use
for showing non-working time.

The Task Usage and Resource Usage view however, use the 'Standard'
calendar for showing non-working time. So no option to show non-working
time from a different calendar in those views.

I hope this helps,
Hans

Projectopolis <http://msepm.hsquared.be>


alm80 wrote:
> Hello,
> I need to change the working week to start on Sunday, and end on Thursday,
> so that Friday and Saturday are days off. When I change this in "Change
> Working Time", this has no effect on the calendar itself. I see
> Saturdays/Sundays as days off. Is there any way to change also the visual
> settings of the calendar to reflect this change. I can set those manually
> with non-standard working time, etc. But it's a lot of work for multi-month
> projects. I'd like this option to be set as default.
>
From: JulieS on
One quick clarification. The display of non-working time in the Task
and Resource Usage views can be changed through Format > Timescale,
Nonworking time tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 2/1/2010 10:07 AM, HansH wrote:
> Using "Change Working Time", you can specify the work week you need
> (Friday = non-working and Sunday = specific working times).
> To visually show these changes in the Gantt Chart, right-click the Gantt
> Chart and select Non-Working Time. You can specify the calendar to use
> for showing non-working time.
>
> The Task Usage and Resource Usage view however, use the 'Standard'
> calendar for showing non-working time. So no option to show non-working
> time from a different calendar in those views.
>
> I hope this helps,
> Hans
>
> Projectopolis <http://msepm.hsquared.be>
>
>
> alm80 wrote:
>> Hello,
>> I need to change the working week to start on Sunday, and end on Thursday,
>> so that Friday and Saturday are days off. When I change this in "Change
>> Working Time", this has no effect on the calendar itself. I see
>> Saturdays/Sundays as days off. Is there any way to change also the visual
>> settings of the calendar to reflect this change. I can set those manually
>> with non-standard working time, etc. But it's a lot of work for multi-month
>> projects. I'd like this option to be set as default.
>>
From: HansH on
Thank you Julie. Totally forgot about that option... so I was a little
too fast with my response.

Projectopolis <http://msepm.hsquared.be>


JulieS wrote:
> One quick clarification. The display of non-working time in the Task
> and Resource Usage views can be changed through Format > Timescale,
> Nonworking time tab.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional
> information about Microsoft Project
>
> On 2/1/2010 10:07 AM, HansH wrote:
>> Using "Change Working Time", you can specify the work week you need
>> (Friday = non-working and Sunday = specific working times).
>> To visually show these changes in the Gantt Chart, right-click the Gantt
>> Chart and select Non-Working Time. You can specify the calendar to use
>> for showing non-working time.
>>
>> The Task Usage and Resource Usage view however, use the 'Standard'
>> calendar for showing non-working time. So no option to show non-working
>> time from a different calendar in those views.
>>
>> I hope this helps,
>> Hans
>>
>> Projectopolis <http://msepm.hsquared.be>
>>
>>
>> alm80 wrote:
>>> Hello,
>>> I need to change the working week to start on Sunday, and end on
>>> Thursday,
>>> so that Friday and Saturday are days off. When I change this in "Change
>>> Working Time", this has no effect on the calendar itself. I see
>>> Saturdays/Sundays as days off. Is there any way to change also the
>>> visual
>>> settings of the calendar to reflect this change. I can set those
>>> manually
>>> with non-standard working time, etc. But it's a lot of work for
>>> multi-month
>>> projects. I'd like this option to be set as default.
>>>
From: JulieS on
Not to worry Hans. We all forget stuff :-) Thanks so much for helping
the growing community of users.

Julie
Project MVP

On 2/1/2010 11:23 AM, HansH wrote:
> Thank you Julie. Totally forgot about that option... so I was a little
> too fast with my response.
>
> Projectopolis <http://msepm.hsquared.be>
>
>
> JulieS wrote:
>> One quick clarification. The display of non-working time in the Task
>> and Resource Usage views can be changed through Format > Timescale,
>> Nonworking time tab.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>> On 2/1/2010 10:07 AM, HansH wrote:
>>> Using "Change Working Time", you can specify the work week you need
>>> (Friday = non-working and Sunday = specific working times).
>>> To visually show these changes in the Gantt Chart, right-click the Gantt
>>> Chart and select Non-Working Time. You can specify the calendar to use
>>> for showing non-working time.
>>>
>>> The Task Usage and Resource Usage view however, use the 'Standard'
>>> calendar for showing non-working time. So no option to show non-working
>>> time from a different calendar in those views.
>>>
>>> I hope this helps,
>>> Hans
>>>
>>> Projectopolis <http://msepm.hsquared.be>
>>>
>>>
>>> alm80 wrote:
>>>> Hello,
>>>> I need to change the working week to start on Sunday, and end on
>>>> Thursday,
>>>> so that Friday and Saturday are days off. When I change this in "Change
>>>> Working Time", this has no effect on the calendar itself. I see
>>>> Saturdays/Sundays as days off. Is there any way to change also the
>>>> visual
>>>> settings of the calendar to reflect this change. I can set those
>>>> manually
>>>> with non-standard working time, etc. But it's a lot of work for
>>>> multi-month
>>>> projects. I'd like this option to be set as default.
>>>>