From: Andrew Lavinsky on
You're probably right. I can't recreate the issue, so I'll blame it on temporary
heat stroke. :-)


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm

> Hi Andrew,
>
> I think it's Today's date and Start dates that default to 0800 but the
> Status date to 1500 to include work done that day.
>
> Mike Glen
> Project MVP
> "Andrew Lavinsky" <(Catapult Systems)> wrote in message
> news:c4abab7233a4e8ccc4a8e4234b93(a)msnews.microsoft.com...
> Actually, as I recall, I've found some wackiness where the Status
> Date kind
> of depends on if you display time or not in the Tools > Options
> menu. Without
> time displayed, it calculates as of 5PM. With time displayed, it
> shows up
> as 8AM.
> ...or something like that.
>
> - Andrew Lavinsky
> Blog: http://blogs.catapultsystems.com/epm
>> Status date assumes 5:00 PM. So this will account for the difference
>> on day1. Gret catch Andrew.
>>
>> Jim Aksel, MVP
>>
>> Check out my blog for more information:
>> http://www.msprojectblog.com
>> "Andrew Lavinsky" wrote:
>>> It may be a function with your status date including the first day
>>> of the project, but not having any progress booked. Try messing
>>> with the Status Date to see if that changes anything.
>>>
>>> What numbers are you expecting?
>>>
>>> - Andrew Lavinsky
>>> Blog: http://blogs.catapultsystems.com/epm
>>>> Right after I baseline my project, if I run a Earn Value Management
>>>> report, my EV, AC and PV are different. I would have expect that
>>>> all those values would be the same. Why is it not?
>>>>
>>> .
>>>