From: Silene on 14 Apr 2010 09:09 Where do I change /add dates of my master calendar so it updates automatically in all the projects I use it. I change a holiday date inside of calendar but it only changed in the project I was working on. Txs, Silene :)
From: Andrew Lavinsky on 14 Apr 2010 09:41 If you're not using Project Server, make a new calendar based off of the Standard calendar. Then open the Organizer (Tools > Organizer), and copy the new calendar to the Global.mpt file. That will make the calendar available to all files opened on that specific machine. Follow the same steps to modify the calendar. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > Where do I change /add dates of my master calendar so it updates > automatically in all the projects I use it. > I change a holiday date inside of calendar but it only changed in the > project I was working on. > Txs, > > Silene :) >
|