From: Mahalakshmi on 14 Apr 2010 04:32 I am trying to draw resource histogram for all resources in a project. Right now, if I choose resource graph, I am able view it only for a single resource. I want to view the allocation for all resources for the entire duration of the project.
From: Barbara - Austria on 14 Apr 2010 04:53 Hi Mahalakshmi, here one possibilty how you can get it: - Split window - Select 'Resource Usage' view in the top pane - Select 'Resource Graph' view in the bottom pane - Right click in the bottom pane to open context menu - Open Bar Styles… - Change settings in the left column (Selected resources) from 'Don't Show' to 'Bar' - Change settings in the right column (Resource) from 'Bar' to 'Don't Show' Resource Graph will show allocation for resources selected in top pane. Does that help? Regards Barbara "Mahalakshmi" <Mahalakshmi(a)discussions.microsoft.com> schrieb im Newsbeitrag news:92C6A93A-9B6C-4543-83AE-70DED33FF592(a)microsoft.com... >I am trying to draw resource histogram for all resources in a project. >Right > now, if I choose resource graph, I am able view it only for a single > resource. I want to view the allocation for all resources for the entire > duration of the project.
From: Jan De Messemaeker on 14 Apr 2010 04:57 Hoi, If you want the histogram for the total work of all the resources (one bar per period showing the total only) look at http://www.mvps.org/project/faqs.htm Faq 38: combined resoruce graph However, if you want a stacked histogram, that is not feasible in Project Standard or Professional, only in Project Server. Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Mahalakshmi" <Mahalakshmi(a)discussions.microsoft.com> wrote in message news:92C6A93A-9B6C-4543-83AE-70DED33FF592(a)microsoft.com... >I am trying to draw resource histogram for all resources in a project. >Right > now, if I choose resource graph, I am able view it only for a single > resource. I want to view the allocation for all resources for the entire > duration of the project.
|
Pages: 1 Prev: project 2007 question Next: master calendar |