From: Nick Boot-Handford Nick on
I need to calculate planned % complete so that I can work out the SPI as we
do not monitor cost on this project. What is the formula you use for the
individual bars?

Nick

"Andrew" wrote:

> I have a formula which works out the planned % for individual bars - works
> great. The problem I have is with the summary bars. My formula works in a
> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
> method to calculate the actual % of summary bars - I understand how it does
> it, what I was hoping for is there somebody out there that could issue a
> formula (via a macro) that copies that method, as at the moment the two do
> not correlate.
>
> Thanks in anticipation.
>
> Andrew
From: "Steve House" sjhouse at hotmail dot on
If you do not monitor costs, set all resource standard and overtime rates to
$1. Set the currency format to have no dollar sign. Now you can use the
built-in conventional earned value tools, including SPI, but with them based
on man-hours instead of dollars. "Planned % Complete" doesn't really tell
you much.
--
Steve House
MS Project Trainer & Consultant



"Nick Boot-Handford" <Nick Boot-Handford(a)discussions.microsoft.com> wrote in
message news:76F031A7-5646-47D4-B191-BA2FB82865B3(a)microsoft.com...
>I need to calculate planned % complete so that I can work out the SPI as we
> do not monitor cost on this project. What is the formula you use for the
> individual bars?
>
> Nick
>
> "Andrew" wrote:
>
>> I have a formula which works out the planned % for individual bars -
>> works
>> great. The problem I have is with the summary bars. My formula works in a
>> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
>> method to calculate the actual % of summary bars - I understand how it
>> does
>> it, what I was hoping for is there somebody out there that could issue a
>> formula (via a macro) that copies that method, as at the moment the two
>> do
>> not correlate.
>>
>> Thanks in anticipation.
>>
>> Andrew

From: Nick Boot-Handford Nick on
So how do you set the resource rates?

"Steve House" wrote:

> If you do not monitor costs, set all resource standard and overtime rates to
> $1. Set the currency format to have no dollar sign. Now you can use the
> built-in conventional earned value tools, including SPI, but with them based
> on man-hours instead of dollars. "Planned % Complete" doesn't really tell
> you much.
> --
> Steve House
> MS Project Trainer & Consultant
>
>
>
> "Nick Boot-Handford" <Nick Boot-Handford(a)discussions.microsoft.com> wrote in
> message news:76F031A7-5646-47D4-B191-BA2FB82865B3(a)microsoft.com...
> >I need to calculate planned % complete so that I can work out the SPI as we
> > do not monitor cost on this project. What is the formula you use for the
> > individual bars?
> >
> > Nick
> >
> > "Andrew" wrote:
> >
> >> I have a formula which works out the planned % for individual bars -
> >> works
> >> great. The problem I have is with the summary bars. My formula works in a
> >> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
> >> method to calculate the actual % of summary bars - I understand how it
> >> does
> >> it, what I was hoping for is there somebody out there that could issue a
> >> formula (via a macro) that copies that method, as at the moment the two
> >> do
> >> not correlate.
> >>
> >> Thanks in anticipation.
> >>
> >> Andrew
>
> .
>
From: Rob Schneider on
In the Resource Sheet.


--rms

www.rmschneider.com




On 25/01/10 15:01, Nick Boot-Handford wrote:
> So how do you set the resource rates?
>
> "Steve House" wrote:
>
>> If you do not monitor costs, set all resource standard and overtime rates to
>> $1. Set the currency format to have no dollar sign. Now you can use the
>> built-in conventional earned value tools, including SPI, but with them based
>> on man-hours instead of dollars. "Planned % Complete" doesn't really tell
>> you much.
>> --
>> Steve House
>> MS Project Trainer& Consultant
>>
>>
>>
>> "Nick Boot-Handford"<Nick Boot-Handford(a)discussions.microsoft.com> wrote in
>> message news:76F031A7-5646-47D4-B191-BA2FB82865B3(a)microsoft.com...
>>> I need to calculate planned % complete so that I can work out the SPI as we
>>> do not monitor cost on this project. What is the formula you use for the
>>> individual bars?
>>>
>>> Nick
>>>
>>> "Andrew" wrote:
>>>
>>>> I have a formula which works out the planned % for individual bars -
>>>> works
>>>> great. The problem I have is with the summary bars. My formula works in a
>>>> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
>>>> method to calculate the actual % of summary bars - I understand how it
>>>> does
>>>> it, what I was hoping for is there somebody out there that could issue a
>>>> formula (via a macro) that copies that method, as at the moment the two
>>>> do
>>>> not correlate.
>>>>
>>>> Thanks in anticipation.
>>>>
>>>> Andrew
>>
>> .
>>