From: Andrew on 11 Jan 2010 06:22 I have a formula which works out the planned % for individual bars - works great. The problem I have is with the summary bars. My formula works in a straight line ie 2 days out of 10 = 20%. I know that MSP uses a different method to calculate the actual % of summary bars - I understand how it does it, what I was hoping for is there somebody out there that could issue a formula (via a macro) that copies that method, as at the moment the two do not correlate. Thanks in anticipation. Andrew
From: Rob Schneider on 11 Jan 2010 06:41 Andrew, I don't have any magic formula or macros to contribute to you; however I'm curious why you want to do this when the computations for this and a way to measure progress is already provided in Project? What's the gap? --rms www.rmschneider.com On 11/01/10 11:22, Andrew wrote: > I have a formula which works out the planned % for individual bars - works > great. The problem I have is with the summary bars. My formula works in a > straight line ie 2 days out of 10 = 20%. I know that MSP uses a different > method to calculate the actual % of summary bars - I understand how it does > it, what I was hoping for is there somebody out there that could issue a > formula (via a macro) that copies that method, as at the moment the two do > not correlate. > > Thanks in anticipation. > > Andrew
From: "Steve House" sjhouse at hotmail dot on 11 Jan 2010 12:53 For a summary task Project totals the actual duration worked for the various subtasks and divides by the total of the individual subtask durations. This give the summary % complete. To compute the summary "worked through" date, it subtracts summary % complete from 100% to get summary percent remaining. This is multiplied by summary duration to get summary remaining duration. That amount is subtracted from the summary finish date to get summary worked through date. -- Steve House MS Project Trainer & Consultant "Andrew" <Andrew(a)discussions.microsoft.com> wrote in message news:57A24738-F8D3-46AA-AD37-98773A827578(a)microsoft.com... >I have a formula which works out the planned % for individual bars - works > great. The problem I have is with the summary bars. My formula works in a > straight line ie 2 days out of 10 = 20%. I know that MSP uses a different > method to calculate the actual % of summary bars - I understand how it > does > it, what I was hoping for is there somebody out there that could issue a > formula (via a macro) that copies that method, as at the moment the two do > not correlate. > > Thanks in anticipation. > > Andrew
From: Jim Aksel on 11 Jan 2010 15:28 Please visit my blog and download the white paper on "What Percent Complete Should I Be?" -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "Andrew" wrote: > I have a formula which works out the planned % for individual bars - works > great. The problem I have is with the summary bars. My formula works in a > straight line ie 2 days out of 10 = 20%. I know that MSP uses a different > method to calculate the actual % of summary bars - I understand how it does > it, what I was hoping for is there somebody out there that could issue a > formula (via a macro) that copies that method, as at the moment the two do > not correlate. > > Thanks in anticipation. > > Andrew
From: Andrew on 18 Jan 2010 10:19
Rob, Steve & Jim Firstly thankyou for taking the time to reply. Rob - the problem occurs when I am trying to establish the planned part for summary bars only. I work for a construction company, our site teams and my Directors want to know on a high level basis a comparison of where we should be to where we are on a % basis. I am unaware of any function inbuilt within MSP that will do this hence the need for a macro - only it just does not work on Summary bars as MSP works out the actual % complete in a different way and I have been unable to replicate it. Steve - I understand how MSP does this, but I am unable to replicate the mechanism in a macro. Jim - Downloaded your white paper. hence the delay in replying - thankyou very much for that as it explains the mechanisms used very well - tried all the formulas and managed to get the summary bar % to work. Not sure about the minutes per day though. Thank you all for your advice & help Andrew "Jim Aksel" wrote: > Please visit my blog and download the white paper on "What Percent Complete > Should I Be?" > > -- > If this post was helpful, please consider rating it. > > Jim Aksel, MVP > > Check out my blog for more information: > http://www.msprojectblog.com > > > > "Andrew" wrote: > > > I have a formula which works out the planned % for individual bars - works > > great. The problem I have is with the summary bars. My formula works in a > > straight line ie 2 days out of 10 = 20%. I know that MSP uses a different > > method to calculate the actual % of summary bars - I understand how it does > > it, what I was hoping for is there somebody out there that could issue a > > formula (via a macro) that copies that method, as at the moment the two do > > not correlate. > > > > Thanks in anticipation. > > > > Andrew |