From: Andrew on
I have a formula which works out the planned % for individual bars - works
great. The problem I have is with the summary bars. My formula works in a
straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
method to calculate the actual % of summary bars - I understand how it does
it, what I was hoping for is there somebody out there that could issue a
formula (via a macro) that copies that method, as at the moment the two do
not correlate.

Thanks in anticipation.

Andrew
From: Rob Schneider on
Andrew,

I don't have any magic formula or macros to contribute to you; however
I'm curious why you want to do this when the computations for this and a
way to measure progress is already provided in Project? What's the gap?

--rms

www.rmschneider.com




On 11/01/10 11:22, Andrew wrote:
> I have a formula which works out the planned % for individual bars - works
> great. The problem I have is with the summary bars. My formula works in a
> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
> method to calculate the actual % of summary bars - I understand how it does
> it, what I was hoping for is there somebody out there that could issue a
> formula (via a macro) that copies that method, as at the moment the two do
> not correlate.
>
> Thanks in anticipation.
>
> Andrew
From: "Steve House" sjhouse at hotmail dot on
For a summary task Project totals the actual duration worked for the various
subtasks and divides by the total of the individual subtask durations. This
give the summary % complete. To compute the summary "worked through" date,
it subtracts summary % complete from 100% to get summary percent remaining.
This is multiplied by summary duration to get summary remaining duration.
That amount is subtracted from the summary finish date to get summary worked
through date.

--
Steve House
MS Project Trainer & Consultant


"Andrew" <Andrew(a)discussions.microsoft.com> wrote in message
news:57A24738-F8D3-46AA-AD37-98773A827578(a)microsoft.com...
>I have a formula which works out the planned % for individual bars - works
> great. The problem I have is with the summary bars. My formula works in a
> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
> method to calculate the actual % of summary bars - I understand how it
> does
> it, what I was hoping for is there somebody out there that could issue a
> formula (via a macro) that copies that method, as at the moment the two do
> not correlate.
>
> Thanks in anticipation.
>
> Andrew

From: Jim Aksel on
Please visit my blog and download the white paper on "What Percent Complete
Should I Be?"

--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Andrew" wrote:

> I have a formula which works out the planned % for individual bars - works
> great. The problem I have is with the summary bars. My formula works in a
> straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
> method to calculate the actual % of summary bars - I understand how it does
> it, what I was hoping for is there somebody out there that could issue a
> formula (via a macro) that copies that method, as at the moment the two do
> not correlate.
>
> Thanks in anticipation.
>
> Andrew
From: Andrew on
Rob, Steve & Jim

Firstly thankyou for taking the time to reply.

Rob - the problem occurs when I am trying to establish the planned part for
summary bars only. I work for a construction company, our site teams and my
Directors want to know on a high level basis a comparison of where we should
be to where we are on a % basis. I am unaware of any function inbuilt within
MSP that will do this hence the need for a macro - only it just does not work
on Summary bars as MSP works out the actual % complete in a different way and
I have been unable to replicate it.

Steve - I understand how MSP does this, but I am unable to replicate the
mechanism in a macro.

Jim - Downloaded your white paper. hence the delay in replying - thankyou
very much for that as it explains the mechanisms used very well - tried all
the formulas and managed to get the summary bar % to work. Not sure about the
minutes per day though. Thank you all for your advice & help

Andrew


"Jim Aksel" wrote:

> Please visit my blog and download the white paper on "What Percent Complete
> Should I Be?"
>
> --
> If this post was helpful, please consider rating it.
>
> Jim Aksel, MVP
>
> Check out my blog for more information:
> http://www.msprojectblog.com
>
>
>
> "Andrew" wrote:
>
> > I have a formula which works out the planned % for individual bars - works
> > great. The problem I have is with the summary bars. My formula works in a
> > straight line ie 2 days out of 10 = 20%. I know that MSP uses a different
> > method to calculate the actual % of summary bars - I understand how it does
> > it, what I was hoping for is there somebody out there that could issue a
> > formula (via a macro) that copies that method, as at the moment the two do
> > not correlate.
> >
> > Thanks in anticipation.
> >
> > Andrew