From: Tammy B Tammy on 16 Feb 2010 16:48 The Resource Usage Sheet is showing all of my milestones as unassigned tasks. Is there a way to modify this so that it does not consider milestones on the Resource Usage sheet?
From: JulieS on 16 Feb 2010 17:08
Hello Tammy, I assume you mean you are seeing the milestones under the grouping "Unassigned" in the Resource Usage view. This is expected if you do not assign resources to the milestones (and I personally do not). Unfortunately it does not appear that a simple filter for Name <> "Unassigned" works. The only way I could hide the tasks was to drop a Flag field and set the milestone tasks to "Yes" and then filter for Flag1= "No". I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 2/16/2010 4:48 PM, Tammy B wrote: > The Resource Usage Sheet is showing all of my milestones as unassigned tasks. > Is there a way to modify this so that it does not consider milestones on the > Resource Usage sheet? |