From: jp on

Hi,

I'm updating tasks with actual hours spent each week on tasks.
How do I change the display on the "Actual Dur" from days to hours?
If a developer has worked 4 hour on a task that takes 5 days it displays
..5d under "Actual Dur". I would like to see it as 4 hrs?

-jp
From: Andrew Lavinsky on
Why don't you just display the Actual Work column?

"jp" wrote:

>
> Hi,
>
> I'm updating tasks with actual hours spent each week on tasks.
> How do I change the display on the "Actual Dur" from days to hours?
> If a developer has worked 4 hour on a task that takes 5 days it displays
> .5d under "Actual Dur". I would like to see it as 4 hrs?
>
> -jp
From: jp on

Hi Andrew,

Thanks for replying to my email question. I added the "Actual Work" column
but it is not already populated with any hours, even though I have been
updating the task.
Do the hours not populate automatically when that column is added?

-JP

"Andrew Lavinsky" wrote:

> Why don't you just display the Actual Work column?
>
> "jp" wrote:
>
> >
> > Hi,
> >
> > I'm updating tasks with actual hours spent each week on tasks.
> > How do I change the display on the "Actual Dur" from days to hours?
> > If a developer has worked 4 hour on a task that takes 5 days it displays
> > .5d under "Actual Dur". I would like to see it as 4 hrs?
> >
> > -jp
From: Jan De Messemaeker on
Hi,

Tools, Macro, Macros, Format_Duration, Run.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"jp" <jp(a)discussions.microsoft.com> wrote in message
news:1DFDC7A3-8DF3-49AD-AFA8-23F50928DDC4(a)microsoft.com...
>
> Hi Andrew,
>
> Thanks for replying to my email question. I added the "Actual Work"
> column
> but it is not already populated with any hours, even though I have been
> updating the task.
> Do the hours not populate automatically when that column is added?
>
> -JP
>
> "Andrew Lavinsky" wrote:
>
>> Why don't you just display the Actual Work column?
>>
>> "jp" wrote:
>>
>> >
>> > Hi,
>> >
>> > I'm updating tasks with actual hours spent each week on tasks.
>> > How do I change the display on the "Actual Dur" from days to hours?
>> > If a developer has worked 4 hour on a task that takes 5 days it
>> > displays
>> > .5d under "Actual Dur". I would like to see it as 4 hrs?
>> >
>> > -jp


From: JulieS on
Hello JP,

Pardon me for bumping in. Actual Work should be automatically
calculated if you are tracking actual duration and (1) you have
assigned work resources to the tasks and (2) the option "Updating
task status updates resources status" on the Calculation tab in
Tools > Options is enabled (checked).

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 4/3/2010 12:36 AM, jp wrote:
>
> Hi Andrew,
>
> Thanks for replying to my email question. I added the "Actual Work" column
> but it is not already populated with any hours, even though I have been
> updating the task.
> Do the hours not populate automatically when that column is added?
>
> -JP
>
> "Andrew Lavinsky" wrote:
>
>> Why don't you just display the Actual Work column?
>>
>> "jp" wrote:
>>
>>>
>>> Hi,
>>>
>>> I'm updating tasks with actual hours spent each week on tasks.
>>> How do I change the display on the "Actual Dur" from days to hours?
>>> If a developer has worked 4 hour on a task that takes 5 days it displays
>>> .5d under "Actual Dur". I would like to see it as 4 hrs?
>>>
>>> -jp