From: Goobie on 3 Feb 2010 14:03 I apologize. I meant the lag was a % not a % complete. If I change the value in the lag box will it automatically turn the percent into a duration? And what do you mean by double click on link? Do you mean task? On Feb 3, 11:41 am, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: > Lag can be specified in days or percentage. To edit/change double click the > link and change the value in the lag box. Or simply edit the percentage. > > There are a few reasons to use percentage lag. It responds better to tasks > that you know have a variable duration for example, but in general I prefer > to keep things very simple and avoid putting any sort of lag on tasks. > > -Jack Dahlgrenhttp://zo-d.com/blog > > "Goobie" <amber.whitm...(a)yahoo.com> wrote in message > > news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com... > > > > > I have already done my lag time in days. Today I opened an existing > > plan of someone else's and saw that some of their lag time had % > > complete and some had days. Why would you want to do this? > > > Is there anyway I can change the % complete into days? > > When I have tried it has been changing the task I am on...not the > > succesor.- Hide quoted text - > > - Show quoted text -
From: Jack Dahlgren MVP on 3 Feb 2010 14:35 In the gantt chart, double click on the link between the two tasks. Or look in the predecessors or successors field and edit there. -Jack "Goobie" <amber.whitmire(a)yahoo.com> wrote in message news:01898b35-741f-451b-9b87-be48a31bf80e(a)z41g2000yqz.googlegroups.com... > I apologize. I meant the lag was a % not a % complete. If I change the > value in the lag box will it automatically turn the percent into a > duration? > And what do you mean by double click on link? Do you mean task? > On Feb 3, 11:41 am, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: >> Lag can be specified in days or percentage. To edit/change double click >> the >> link and change the value in the lag box. Or simply edit the percentage. >> >> There are a few reasons to use percentage lag. It responds better to >> tasks >> that you know have a variable duration for example, but in general I >> prefer >> to keep things very simple and avoid putting any sort of lag on tasks. >> >> -Jack Dahlgrenhttp://zo-d.com/blog >> >> "Goobie" <amber.whitm...(a)yahoo.com> wrote in message >> >> news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com... >> >> >> >> > I have already done my lag time in days. Today I opened an existing >> > plan of someone else's and saw that some of their lag time had % >> > complete and some had days. Why would you want to do this? >> >> > Is there anyway I can change the % complete into days? >> > When I have tried it has been changing the task I am on...not the >> > succesor.- Hide quoted text - >> >> - Show quoted text - >
From: Goobie on 3 Feb 2010 14:39 If I do that though I have to manually figure out what 10% equals in duration though. And when I do that it is changing the pred date..not the succesors.On Feb 3, 1:35 pm, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: > In the gantt chart, double click on the link between the two tasks. > Or look in the predecessors or successors field and edit there. > > -Jack > > "Goobie" <amber.whitm...(a)yahoo.com> wrote in message > > news:01898b35-741f-451b-9b87-be48a31bf80e(a)z41g2000yqz.googlegroups.com... > > > > > I apologize. I meant the lag was a % not a % complete. If I change the > > value in the lag box will it automatically turn the percent into a > > duration? > > And what do you mean by double click on link? Do you mean task? > > On Feb 3, 11:41 am, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: > >> Lag can be specified in days or percentage. To edit/change double click > >> the > >> link and change the value in the lag box. Or simply edit the percentage. > > >> There are a few reasons to use percentage lag. It responds better to > >> tasks > >> that you know have a variable duration for example, but in general I > >> prefer > >> to keep things very simple and avoid putting any sort of lag on tasks. > > >> -Jack Dahlgrenhttp://zo-d.com/blog > > >> "Goobie" <amber.whitm...(a)yahoo.com> wrote in message > > >>news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com.... > > >> > I have already done my lag time in days. Today I opened an existing > >> > plan of someone else's and saw that some of their lag time had % > >> > complete and some had days. Why would you want to do this? > > >> > Is there anyway I can change the % complete into days? > >> > When I have tried it has been changing the task I am on...not the > >> > succesor.- Hide quoted text - > > >> - Show quoted text -- Hide quoted text - > > - Show quoted text -
From: Jack Dahlgren MVP on 3 Feb 2010 15:20 Yes, you will have to figure out what that lag should be. Beyond that you need to know why there is a lag. Project can't help you with that. This is one reason I would rather use a dummy task instead of a lag. -Jack "Goobie" <amber.whitmire(a)yahoo.com> wrote in message news:cdff3f0f-7532-4699-9a52-0b98492023fb(a)p24g2000yqm.googlegroups.com... > If I do that though I have to manually figure out what 10% equals in > duration though. And when I do that it is changing the pred date..not > the succesors.On Feb 3, 1:35 pm, "Jack Dahlgren MVP" <j...(a)zo-d.com> > wrote: >> In the gantt chart, double click on the link between the two tasks. >> Or look in the predecessors or successors field and edit there. >> >> -Jack >> >> "Goobie" <amber.whitm...(a)yahoo.com> wrote in message >> >> news:01898b35-741f-451b-9b87-be48a31bf80e(a)z41g2000yqz.googlegroups.com... >> >> >> >> > I apologize. I meant the lag was a % not a % complete. If I change the >> > value in the lag box will it automatically turn the percent into a >> > duration? >> > And what do you mean by double click on link? Do you mean task? >> > On Feb 3, 11:41 am, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: >> >> Lag can be specified in days or percentage. To edit/change double >> >> click >> >> the >> >> link and change the value in the lag box. Or simply edit the >> >> percentage. >> >> >> There are a few reasons to use percentage lag. It responds better to >> >> tasks >> >> that you know have a variable duration for example, but in general I >> >> prefer >> >> to keep things very simple and avoid putting any sort of lag on tasks. >> >> >> -Jack Dahlgrenhttp://zo-d.com/blog >> >> >> "Goobie" <amber.whitm...(a)yahoo.com> wrote in message >> >> >>news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com... >> >> >> > I have already done my lag time in days. Today I opened an existing >> >> > plan of someone else's and saw that some of their lag time had % >> >> > complete and some had days. Why would you want to do this? >> >> >> > Is there anyway I can change the % complete into days? >> >> > When I have tried it has been changing the task I am on...not the >> >> > succesor.- Hide quoted text - >> >> >> - Show quoted text -- Hide quoted text - >> >> - Show quoted text - >
From: Goobie on 3 Feb 2010 15:34 This is my third day on the job & I am just trying to clean up a Project Plan I inherited. LOL So guess I will have to go find the task owners and get educated. I was hoping for an easy fix. LOL On Feb 3, 2:20 pm, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: > Yes, you will have to figure out what that lag should be. Beyond that you > need to know why there is a lag. > Project can't help you with that. This is one reason I would rather use a > dummy task instead of a lag. > > -Jack > > "Goobie" <amber.whitm...(a)yahoo.com> wrote in message > > news:cdff3f0f-7532-4699-9a52-0b98492023fb(a)p24g2000yqm.googlegroups.com... > > > > > If I do that though I have to manually figure out what 10% equals in > > duration though. And when I do that it is changing the pred date..not > > the succesors.On Feb 3, 1:35 pm, "Jack Dahlgren MVP" <j...(a)zo-d.com> > > wrote: > >> In the gantt chart, double click on the link between the two tasks. > >> Or look in the predecessors or successors field and edit there. > > >> -Jack > > >> "Goobie" <amber.whitm...(a)yahoo.com> wrote in message > > >>news:01898b35-741f-451b-9b87-be48a31bf80e(a)z41g2000yqz.googlegroups.com.... > > >> > I apologize. I meant the lag was a % not a % complete. If I change the > >> > value in the lag box will it automatically turn the percent into a > >> > duration? > >> > And what do you mean by double click on link? Do you mean task? > >> > On Feb 3, 11:41 am, "Jack Dahlgren MVP" <j...(a)zo-d.com> wrote: > >> >> Lag can be specified in days or percentage. To edit/change double > >> >> click > >> >> the > >> >> link and change the value in the lag box. Or simply edit the > >> >> percentage. > > >> >> There are a few reasons to use percentage lag. It responds better to > >> >> tasks > >> >> that you know have a variable duration for example, but in general I > >> >> prefer > >> >> to keep things very simple and avoid putting any sort of lag on tasks. > > >> >> -Jack Dahlgrenhttp://zo-d.com/blog > > >> >> "Goobie" <amber.whitm...(a)yahoo.com> wrote in message > > >> >>news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com... > > >> >> > I have already done my lag time in days. Today I opened an existing > >> >> > plan of someone else's and saw that some of their lag time had % > >> >> > complete and some had days. Why would you want to do this? > > >> >> > Is there anyway I can change the % complete into days? > >> >> > When I have tried it has been changing the task I am on...not the > >> >> > succesor.- Hide quoted text - > > >> >> - Show quoted text -- Hide quoted text - > > >> - Show quoted text -- Hide quoted text - > > - Show quoted text -
First
|
Prev
|
Next
|
Last
Pages: 1 2 3 Prev: Project 2007: Is there any limit on the number of tasks/resources? Next: www.amiproject.com |