From: Goobie on
I have already done my lag time in days. Today I opened an existing
plan of someone else's and saw that some of their lag time had %
complete and some had days. Why would you want to do this?

Is there anyway I can change the % complete into days?
When I have tried it has been changing the task I am on...not the
succesor.
From: "Steve House" sjhouse at hotmail dot on
Lag time with % complete????? Just what are you seeing? How were the lag
times created?


--
Steve House
MS Project Trainer & Consultant

"Goobie" <amber.whitmire(a)yahoo.com> wrote in message
news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com...
>I have already done my lag time in days. Today I opened an existing
> plan of someone else's and saw that some of their lag time had %
> complete and some had days. Why would you want to do this?
>
> Is there anyway I can change the % complete into days?
> When I have tried it has been changing the task I am on...not the
> succesor.

From: Jan De Messemaeker on
Hi,

It's not a %complete, but % of the predecessor's duration.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Goobie" <amber.whitmire(a)yahoo.com> wrote in message
news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com...
>I have already done my lag time in days. Today I opened an existing
> plan of someone else's and saw that some of their lag time had %
> complete and some had days. Why would you want to do this?
>
> Is there anyway I can change the % complete into days?
> When I have tried it has been changing the task I am on...not the
> succesor.


From: Jack Dahlgren MVP on
Lag can be specified in days or percentage. To edit/change double click the
link and change the value in the lag box. Or simply edit the percentage.

There are a few reasons to use percentage lag. It responds better to tasks
that you know have a variable duration for example, but in general I prefer
to keep things very simple and avoid putting any sort of lag on tasks.

-Jack Dahlgren
http://zo-d.com/blog


"Goobie" <amber.whitmire(a)yahoo.com> wrote in message
news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com...
> I have already done my lag time in days. Today I opened an existing
> plan of someone else's and saw that some of their lag time had %
> complete and some had days. Why would you want to do this?
>
> Is there anyway I can change the % complete into days?
> When I have tried it has been changing the task I am on...not the
> succesor.

From: Mike Glen on
Good grief! I'm still finding new things in Project. Good one Jack

Mike Glen
Project MVP


hi "Jack Dahlgren MVP" <jack(a)zo-d.com> wrote in message news:%23zsdwgPpKHA.5224(a)TK2MSFTNGP05.phx.gbl...
Lag can be specified in days or percentage. To edit/change double click the
link and change the value in the lag box. Or simply edit the percentage.

There are a few reasons to use percentage lag. It responds better to tasks
that you know have a variable duration for example, but in general I prefer
to keep things very simple and avoid putting any sort of lag on tasks.

-Jack Dahlgren
http://zo-d.com/blog


"Goobie" <amber.whitmire(a)yahoo.com> wrote in message
news:77656d0c-b1af-41d7-947c-d113507d64b6(a)u41g2000yqe.googlegroups.com...
> I have already done my lag time in days. Today I opened an existing
> plan of someone else's and saw that some of their lag time had %
> complete and some had days. Why would you want to do this?
>
> Is there anyway I can change the % complete into days?
> When I have tried it has been changing the task I am on...not the
> succesor.