From: svt4cobra6 on 13 Apr 2010 17:02 Hi I have a task that I split because I need to assign different resources to the task during different times, for example I have two summer hires so will asign the task to them only through the summer and to someone else for all other parts of the year. The task runs Jan 2011 to Jan 2012. Thanks
From: Jim Aksel on 13 Apr 2010 20:19 You can do this without splitting the task. Assign "Worker", Student1, Student2 to the task. Go to the task in Task Usage View. For that task you will see all three workers listed. You may change the value of Work on the right side of the sheet. If necessary, you can change the timescale by right clicking. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "svt4cobra6" wrote: > Hi I have a task that I split because I need to assign different resources to > the task during different times, for example I have two summer hires so will > asign the task to them only through the summer and to someone else for all > other parts of the year. The task runs Jan 2011 to Jan 2012. > Thanks
From: lostminder on 14 Apr 2010 12:04 Open Resource Sheet View, double click on the Summer Helpers resource to open Resource Information dialog box, define Resource Availability by filling out Available From and Available To cells, then click Change Working Time, Exception tab to define the dates Summer Helpers don't work. You need to define two nonworking period segments, the first one is from 01/01/2010 of your task to the date before Summer Helpers become available, the second one is from the date when Summer Helpers are non-available to 12/31/2010. You need to go through the above steps to define Resource Availability and Exceptions for Non-Summer Helpers. In Resource Availability, you fill out two sets of Available from and Availabe to, then define one exception for the period when Summer Helpers work. After you have completed the steps to define the availabilities of all your resources, then assign them to the task. You can check your resource assignment by opening Resource Usage view. You don't need to split your task in this way. "svt4cobra6" wrote: > Hi I have a task that I split because I need to assign different resources to > the task during different times, for example I have two summer hires so will > asign the task to them only through the summer and to someone else for all > other parts of the year. The task runs Jan 2011 to Jan 2012. > Thanks
From: svt4cobra6 on 14 Apr 2010 12:07 ok thanks, it worked. Also just wondering if you know if you can set a workers range of availability, possibly in the resource sheet? For example students are only available from June1 through Sept1, thanks. "lostminder" wrote: > Open Resource Sheet View, double click on the Summer Helpers resource to open > Resource Information dialog box, define Resource Availability by filling out > Available From and Available To cells, then click Change Working Time, > Exception tab to define the dates Summer Helpers don't work. You need to > define two nonworking period segments, the first one is from 01/01/2010 of > your task to the date before Summer Helpers become available, the second one > is from the date when Summer Helpers are non-available to 12/31/2010. > You need to go through the above steps to define Resource Availability and > Exceptions for Non-Summer Helpers. In Resource Availability, you fill out two > sets of Available from and Availabe to, then define one exception for the > period when Summer Helpers work. > After you have completed the steps to define the availabilities of all your > resources, then assign them to the task. You can check your resource > assignment by opening Resource Usage view. > You don't need to split your task in this way. > > > "svt4cobra6" wrote: > > > Hi I have a task that I split because I need to assign different resources to > > the task during different times, for example I have two summer hires so will > > asign the task to them only through the summer and to someone else for all > > other parts of the year. The task runs Jan 2011 to Jan 2012. > > Thanks
From: lostminder on 14 Apr 2010 12:27 You need to double click your resource name in Resource Sheet view to open Resource Information dialog box, then do it from there. "svt4cobra6" wrote: > ok thanks, it worked. Also just wondering if you know if you can set a > workers range of availability, possibly in the resource sheet? For example > students are only available from June1 through Sept1, thanks. > > "lostminder" wrote: > > > Open Resource Sheet View, double click on the Summer Helpers resource to open > > Resource Information dialog box, define Resource Availability by filling out > > Available From and Available To cells, then click Change Working Time, > > Exception tab to define the dates Summer Helpers don't work. You need to > > define two nonworking period segments, the first one is from 01/01/2010 of > > your task to the date before Summer Helpers become available, the second one > > is from the date when Summer Helpers are non-available to 12/31/2010. > > You need to go through the above steps to define Resource Availability and > > Exceptions for Non-Summer Helpers. In Resource Availability, you fill out two > > sets of Available from and Availabe to, then define one exception for the > > period when Summer Helpers work. > > After you have completed the steps to define the availabilities of all your > > resources, then assign them to the task. You can check your resource > > assignment by opening Resource Usage view. > > You don't need to split your task in this way. > > > > > > "svt4cobra6" wrote: > > > > > Hi I have a task that I split because I need to assign different resources to > > > the task during different times, for example I have two summer hires so will > > > asign the task to them only through the summer and to someone else for all > > > other parts of the year. The task runs Jan 2011 to Jan 2012. > > > Thanks
|
Next
|
Last
Pages: 1 2 Prev: Baseline Reference Points Next: How do I draw resource histogram for all resources |