Prev: Commas and other separator characters in Custom Text Fields
Next: Project 2010 compatible with Project 2000?
From: KTA on 20 May 2010 20:13 Hi, We are working on large program with Master Program Schedule that has different stream of work inserted projects. Most of the tasks/activities are linked within their phases and have no external links. The Phases are also not linked as most of them have different starting dates and there is no sequencing in them. I need to draw Network diagram and generate a Program Critical Path. When i do so, it appears with very weird diagram that doesn't depict reality and skip few streams of work all together. When i choose the option, show multiple critical paths, it comes up with almost everything is critical. So is there any better way of doing it Or am i missing something fundamental in terms of task(s) or phase linking. Looking forward to hearing from experts. thanks in advance. Regards, KTA
From: Rob Schneider on 21 May 2010 02:15 Without looking at what you have it's only speculation; my hunch is that since you have the different streams of work (in subprojects) were are not linked you ar using date constraints to control the dates. When you do that, you destroy Project's capability to compute the critical path, as you have seen. --rms www.rmschneider.com On 21/05/10 01:13, KTA wrote: > Hi, > > We are working on large program with Master Program Schedule that has > different stream of work inserted projects. Most of the tasks/activities are > linked within their phases and have no external links. The Phases are also > not linked as most of them have different starting dates and there is no > sequencing in them. > > I need to draw Network diagram and generate a Program Critical Path. When i > do so, it appears with very weird diagram that doesn't depict reality and > skip few streams of work all together. > > When i choose the option, show multiple critical paths, it comes up with > almost everything is critical. > > So is there any better way of doing it Or am i missing something fundamental > in terms of task(s) or phase linking. > > Looking forward to hearing from experts. > > thanks in advance. > > Regards, > > KTA >
From: Trevor Rabey on 21 May 2010 03:21 Your instinct is probably right and you probably are missing something fundamental about predecessors, successors and the critical path. Are we talking about a mpp file with other mpp files inserted into it? Does every task have at least one FS predecessor and at least one FS successor? Do any of the tasks have predecessor/successor links with lag, positive or negative? Do any tasks have any date constraint, ie is everything ASAP? I suspect that you have many tasks with no successor. You can check easily by inserting the Successors column/field or Windows, Split and then select the Predecessors and Successors form (by right-clicking on the grey area to the right). If you send the file(s) I will have a look. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "KTA" <KTA(a)discussions.microsoft.com> wrote in message news:10A2B69F-D881-4496-8CD6-E515EBC38817(a)microsoft.com... > Hi, > > We are working on large program with Master Program Schedule that has > different stream of work inserted projects. Most of the tasks/activities > are > linked within their phases and have no external links. The Phases are also > not linked as most of them have different starting dates and there is no > sequencing in them. > > I need to draw Network diagram and generate a Program Critical Path. When > i > do so, it appears with very weird diagram that doesn't depict reality and > skip few streams of work all together. > > When i choose the option, show multiple critical paths, it comes up with > almost everything is critical. > > So is there any better way of doing it Or am i missing something > fundamental > in terms of task(s) or phase linking. > > Looking forward to hearing from experts. > > thanks in advance. > > Regards, > > KTA >
From: Jim Aksel on 21 May 2010 09:45 In addition to the comments of my peers, please check these items as well -- Unconstrained Start Dates. Trevor said to make sure each task has at least one FS predecessor and successor. In addition, make sure each subproject mpp file has two milestones: "Subproject Start" and "Subproject Finish." Using Trevor's advice, every task in the file must be traced to both of these milestones along a path. Calendars: There are really multiple calendars involved, one for each subproject and one for the master. This can create problems, especially if the subprojects have different start dates (Project/Project Information...). Try to use the same calendar if possible. Since your subprojects have different start dates, then consider using the date constraint "Start No Earlier Than" on the "Subproject Start" milestones. Remember, you are not going to get a real "total program critical path" until there are links between the subproject files. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "KTA" wrote: > Hi, > > We are working on large program with Master Program Schedule that has > different stream of work inserted projects. Most of the tasks/activities are > linked within their phases and have no external links. The Phases are also > not linked as most of them have different starting dates and there is no > sequencing in them. > > I need to draw Network diagram and generate a Program Critical Path. When i > do so, it appears with very weird diagram that doesn't depict reality and > skip few streams of work all together. > > When i choose the option, show multiple critical paths, it comes up with > almost everything is critical. > > So is there any better way of doing it Or am i missing something fundamental > in terms of task(s) or phase linking. > > Looking forward to hearing from experts. > > thanks in advance. > > Regards, > > KTA >
From: KTA on 23 May 2010 22:41 Hi, Thanks for your time and valuable advices. As i explained I am using Master Project with the same identical calendar that is being used by individual inserted projects. My Program Structure is like; MASTER PROGRAM PROJECT A Phase 1 T1 T2 (FS Dependency) T3 (FS Dependency) Phase 2 T4 T5 (FS Dependency) Phase 3 T6 T7 (FS Dependency) PROJECT B Phase 1 T1 T2 (FS Dependency) T3 (FS Dependency) Phase 2 T4 T5 (FS Dependency) Phase 3 T6 T7 (FS Dependency) PROJECT C Phase 1 T1 T2 (FS Dependency) T3 (FS Dependency) Phase 2 T4 T5 (FS Dependency) Phase 3 T6 T7 (FS Dependency) 1. All tasks are linked within their respect Phases and our not linked to any task in the next phase because all of the phases have different start dates and there are no logical sequencing. 2. There are some tasks which are linked as an external predcessors i.e. T2 in Project A is linked with T4 in Project B. So my questions are; 1. How should i link the tasks outside the phases to get a proper critical path. 2. Should i constraint the task with Start No Earlier Than with a specific date but there are no logical relationship of one phase ending and the other phase starting. Your responses will be highly appreciated.
|
Next
|
Last
Pages: 1 2 Prev: Commas and other separator characters in Custom Text Fields Next: Project 2010 compatible with Project 2000? |