From: RVE on 23 Feb 2010 17:07 Is there any way to make an entire week a non-working work week? As in, a task is going to take 25 days, but the 4th of July occurs in the middle and you want to show that during that week (or 2), no work will occur. Besides creating a new task or extending the task during. Thanks in advance!
From: DavidC on 23 Feb 2010 18:22
Hi RVE, Open up the calendar, "Tools", 'Change working time..', then simply select the days you want as non working. Make sure that the calendar you change is the Project calendar and is the basis for all other calendars such as individual resource calendars. Hope this helps DavidC "RVE" wrote: > Is there any way to make an entire week a non-working work week? As > in, a task is going to take 25 days, but the 4th of July occurs in the > middle and you want to show that during that week (or 2), no work will > occur. Besides creating a new task or extending the task during. > Thanks in advance! > . > |