Working with microsoft project and project server. We purchased both project and project server a couple of years ago, and we haven't used server since we purchased it. I am trying to facilitate a move to using project server to facilitate our time tracking as well as other needs. In doing this, I don't really know a lot about the operation of server. I'd appre... 1 Apr 2010 12:24
One year task duration Hi, all How can I insert an one year task duration in Project (time unit 1y don't work)? Thanks ---------------- Edward ... 2 Apr 2010 11:31
View multiple baseline gantt How many multiple baselines can be viewed simultaneously? I have baselined for 8 times. Is all possible 11 baselines can be viewed together to analyse project progress ... 1 Apr 2010 12:24
How do I insert a specific number in a gantt bar Hi I,m attempting to insert a specific number into a gantt bar or edit default text in the format box. Any body help? ... 1 Apr 2010 06:50
I can't see Gnatt bars on print preview? The Gnatt task bars don't show up when I try to print to PDF. ... 1 Apr 2010 03:36
changing to a 24 hour calendar I have a project that will run 24 hours a day until it's finished,I can't get the calendar to change to a 24 hour one. how can I change it for this project? ... 1 Apr 2010 19:09
Resource Units Related question: If I set up my project the same way Marni did, but I should have done it the way you describe, in order to 'fix' my project and get MSP to eliminate the 1600% resource allocations, do I re-enter the tasks the 'right' way? "JulieS" wrote: Hi Marni, PMFJI, but no, this isn't a bug i... 1 Apr 2010 06:50
% complete Didn't get any responses to a previous post on this. I would like to be able to show a "simple" % complete. It can be based on elapsed % (as of data date) of total planned duration. Sometimes I would prefer to punch in a %. If I do that now, it changes the end dates and that's not okay. This shouldn't be difficult but... 1 Apr 2010 06:50
Change resource working time for a specific project (ProjectServe Since you are probably talking about Project Server, best to repost where the gurus hang out: microsoft.public.project.server. --rms www.rmschneider.com On 31/03/10 16:39, Yannis wrote: Hello, we need to set a resource to only work for one (1) day per week on a specific project (because... 31 Mar 2010 13:16
Change resource working time for a specific project (Project Serve Hello, we need to set a resource to only work for one (1) day per week on a specific project (because we want to book the rest 4 days to work in another project). [At the Enterprise Pool level, the resource is correctly setup to work five (5) days per week] Is there any way we can achieve this? Thank... 31 Mar 2010 14:23 |