date of task before that date of use of resource Friends, Have a problem with project, but have dates of task that begin before that date of use of resource. For example: Task1 01/12/2010 05/06/2010 Bob 15/5/2010 05/06/2010 I need to see Taks1 15/05/2010 05/06/2010 Bob 15/05... 23 Mar 2010 11:20
Assistance Needed in Comparing 2 MSP versions from differenct sour I am attempting to compare 2 projects in MSP 2003. I have both open and am using the compare functionality. I am aware that the Unique ID field is a key component and have noted that often these do not match for the same line item from one version to the next as different individuals are preparing this projec... 23 Mar 2010 13:41
Start Task two days after Hi, I would like to start a task two days after starting another task. Is that possibloe? Thanks! ... 23 Mar 2010 11:20
task indents How can the number of spaces indented for subtasks be changed in Project? The current indent moves the taks to the right 5+ spaces, where if it was two spaces the indent would still be visible while conserving horizontal real estate. ... 23 Mar 2010 09:00
PS 2007 SP2 - Outline code issue It looks like the SP2 is not able to pick up the outline codes values from an SP1 MPP file. When opening a MPP that was created in SP1 in our SP2 environment, the outline codes values are incorrect. The testers are having to go into the outline codes and re-enter the correct information. Has anyone had the ... 25 Mar 2010 16:16
Saving as PDF Hi i would like to know how i save a file as a PDF or some other format so i can mail a gnat chart to a recepient without the Miccrosoft Project program?? -- RIP! ... 22 Mar 2010 13:06
Sychronise the microsoft project calendar to our calendar Hi, How can we set microsoft project calendar to our calendar? E.g. 3rd Jan 2010 is our WW02 instead of default WW01. -- kelvin ... 22 Mar 2010 11:54
Breaking up the timeline Hi, I have a simple project where the first task takes 28 edays and the following 36 tasks takes 13 days. Is there any way to break up the timeline to that rather than showing 6 weeks (say six inches on paper) of equal length so to speak it, instead show the first 4 weeks as one inch and the remainder as five in... 23 Mar 2010 10:09
Gant Chart Freeze Panes Hi, I would like to see the Task Name column always while scrolling other columns in the Gantt Chart. Something like Freeze Panes in microsoft excel. Can I do that? Is there any provision available in ms project for doing such things? Thanks! ... 21 Mar 2010 20:52
import wbs code Hi, Our organisation uses a list of wbs code. For Eg: wbs code for design prepartion is DES-PRP. Can I import these wbs codes to ms project? Thanks! ... 21 Mar 2010 11:37 |