From: Dale Howard [MVP] on 2 Feb 2010 15:31 IHI -- Precisely where in Microsoft Project do you see this number of hours assigned to each resource? Let us know and we will try to help. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "IHI" <IHI(a)discussions.microsoft.com> wrote in message news:92470697-0036-402D-9796-C54A28793143(a)microsoft.com... > Unfortunately, it didn't. Each resource still has 689 hours assigned to > them > from this task. > > > "Dale Howard [MVP]" wrote: > >> IHI -- >> >> Double-click the recurring task in your project to display the Recurring >> Task Information dialog. In the dialog, select the Calendar pick list >> and >> select the None value, and click the OK button. You do not need to >> select a >> Calendar value for this Recurring Task since Microsoft Project >> automatically >> scheduled the task using the Project Calendar (specified in Project - >> Project Information). If you apply the Resource Usage view, you should >> now >> see that there are only 87 hours of Work assigned to each resource for >> this >> Recurring Task. Do you? Let us know. >> >> -- >> Dale A. Howard [MVP] >> VP of Educational Services >> msProjectExperts >> http://www.msprojectexperts.com >> http://www.projectserverexperts.com >> "We write the books on Project Server" >
From: IHI on 2 Feb 2010 15:50 I'm not sure the exact name of this screen, but when you select Window > Split from the top menu with this recurring task highlighted, each resource has 689h assigned to them. The 689h also appears associated with this Task in the Resource Usage screen, as well as the Task Usage screen, showing 8h per day of work associated with this Task. "Dale Howard [MVP]" wrote: > IHI -- > > Precisely where in Microsoft Project do you see this number of hours > assigned to each resource? Let us know and we will try to help. > > -- > Dale A. Howard [MVP] > VP of Educational Services > msProjectExperts > http://www.msprojectexperts.com > http://www.projectserverexperts.com > "We write the books on Project Server"
From: Jan De Messemaeker on 2 Feb 2010 15:52 Hi, What if you invite the people to EACH individual meeting instead of the recurring task? -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availabliy check: http://users.online.be/prom-ade/Calendar.pdf "IHI" <IHI(a)discussions.microsoft.com> wrote in message news:BE17FD12-E208-478B-AEE4-A9773F7F4828(a)microsoft.com... > I've set up a recurring Task in Project to reflect our daily sync meeting, > 1 > hour a day for 4 months. The pertinent details are below: > > Duration: 1hr > Recurrence Pattern: Daily, Every 1 workday > Range of Recurrence: Start: Thu 1/7/10, End by: Fri 5/7/10 > Calendar: Standard, Scheduling ignores resource calendars > > The problem is that each person invited to this morning meeting is now > assigned 689h of Work time from this task alone. On the advice of another > person on this board, I set each meeting to Fixed Duration of 1hr each, > but > this had no effect on the 689 hours. Can anyone tell me what I'm doing > wrong?
From: "Steve House" sjhouse at hotmail dot on 2 Feb 2010 16:00 You are confusing Hours of Work and Hours of Duration. The rolled-up recurring task for a 1 hour per day daily meeting extending over 4 months does indeed have a summary duration of ~680 hours, the total potential working time in the calendar between the start of the first meeting and the end of the last meeting. But the work of a resource assigned to it is only ~80 man-hours, the time actually in the meetings. You should see about 80 hours per resource in the Work tabel in the REsource sheet, the task usage vew, or the resource usage view. -- Steve House MS Project Trainer & Consultant "IHI" <IHI(a)discussions.microsoft.com> wrote in message news:92470697-0036-402D-9796-C54A28793143(a)microsoft.com... > Unfortunately, it didn't. Each resource still has 689 hours assigned to > them > from this task. > > > "Dale Howard [MVP]" wrote: > >> IHI -- >> >> Double-click the recurring task in your project to display the Recurring >> Task Information dialog. In the dialog, select the Calendar pick list >> and >> select the None value, and click the OK button. You do not need to >> select a >> Calendar value for this Recurring Task since Microsoft Project >> automatically >> scheduled the task using the Project Calendar (specified in Project - >> Project Information). If you apply the Resource Usage view, you should >> now >> see that there are only 87 hours of Work assigned to each resource for >> this >> Recurring Task. Do you? Let us know. >> >> -- >> Dale A. Howard [MVP] >> VP of Educational Services >> msProjectExperts >> http://www.msprojectexperts.com >> http://www.projectserverexperts.com >> "We write the books on Project Server" >
From: IHI on 2 Feb 2010 16:56 All due respect, but that's not the case. Each individual resource is showing 689h assigned to them from this one task. It shows up under their names in the resource sheet, the task usage vew and the resource usage view. If there's a way to send you a screenshot, let me know and I'll show you. "Steve House" wrote: > You are confusing Hours of Work and Hours of Duration. The rolled-up > recurring task for a 1 hour per day daily meeting extending over 4 months > does indeed have a summary duration of ~680 hours, the total potential > working time in the calendar between the start of the first meeting and the > end of the last meeting. But the work of a resource assigned to it is only > ~80 man-hours, the time actually in the meetings. You should see about 80 > hours per resource in the Work tabel in the REsource sheet, the task usage > vew, or the resource usage view. > > > -- > Steve House > MS Project Trainer & Consultant