See my previous note to David. Changing the default start and finish times
in the Tools/Options/Calendar page DOES NOT change the workday start and end
times or influence the working time calendar in any way.
--
Steve House
MS Project Trainer & Consultant

"Roland67" <Roland67(a)discussions.microsoft.com> wrote in message
news:B33B1FCF-ED9D-4053-9768-BF97EE2A403D(a)microsoft.com...
> If you want to change the work time for all tasks/resources then you'd
> want
> to change the work times in Tools--Options area or on the project's
> calendar.
> If its only on a task you'd want to create/update a task calendar which
> allows those hours to be valid work times. Hope this helps.
>
> "DannyG" wrote:
>
>> I want to select specific work times to do work on a project from 9pm to
>> 1am
>> every day but when I tried to do this, the work times I specified would
>> not
>> change.