Prev: Non-working work week
Next: Putting a hold on tasks
From: "Steve House" sjhouse at hotmail dot on 26 Feb 2010 05:28 See my previous note to David. Changing the default start and finish times in the Tools/Options/Calendar page DOES NOT change the workday start and end times or influence the working time calendar in any way. -- Steve House MS Project Trainer & Consultant "Roland67" <Roland67(a)discussions.microsoft.com> wrote in message news:B33B1FCF-ED9D-4053-9768-BF97EE2A403D(a)microsoft.com... > If you want to change the work time for all tasks/resources then you'd > want > to change the work times in Tools--Options area or on the project's > calendar. > If its only on a task you'd want to create/update a task calendar which > allows those hours to be valid work times. Hope this helps. > > "DannyG" wrote: > >> I want to select specific work times to do work on a project from 9pm to >> 1am >> every day but when I tried to do this, the work times I specified would >> not >> change. |