probability that project will we finished two days before planed day in project
On Wed, 9 Dec 2009 00:02:24 -0800 (PST), talar wrote: Hello, I'm trying to find out where Microsoft Project 2007 shows probability or variance for critical task. For eg. I would like to know what is probability that project will be finished on 15 december (planed date is 17 dec). I have calculated PERT... 9 Dec 2009 11:04
Cross project Link
Hi All, I could able to create the "Cross project Link", but how do I view the link details, just I created ? Thanks KS -- ks2008 ------------------------------------------------------------------------ ks2008's Profile: http://forums.techarena.in/members/106957.htm View this thread: http://forums.techarena.in... 11 Dec 2009 18:05
Assigning resource
I have a 20 day task called shutter, steel and concrete on a programme. I am assigning labour resource across the whole activity, however every 4th day i will be concreting, therefore i want to assign a concrete pump every 4th day on this single activity. I do not want to create 5 seperate concreting tasks. ... 9 Dec 2009 09:56
Project with server slow
Hy, We use Project Server 2003 (SP3) and Project pro 2003 (SP3). We have some big projects (14000 tasks). The problem is that when I open this project from server, sometimes after opening it everything is ok and fast, but mostly it is really slow, opening subtask takes about 15 seconds and changing a field (for ex... 9 Dec 2009 04:29
Change Order in Resource Sheet View
In the Resource Sheet View it shows overallocations in RED. Is there a way to sort so those Resources show up at the top? I have hundreds of Resources and I'm always having to scroll up and down to find the overallocations. ... 8 Dec 2009 19:47
Customized Text Fields
I am having a problem seeing the data from customized text fields in the Resource Usage view. For example I have a text field for charge numbers that are assigned to each task. I can view it in the Ghantt Chart. However, when I go to the Resource Usage view and insert that text column the data doesn't appe... 8 Dec 2009 16:27
Having to Level Twice
Has anyone seen it where you need to level twice? I mean I DO have a large Project going on but still. So I Level once and only some of my resources get levelled and all I have to do is level again and then the other get completed. ... 9 Dec 2009 15:33
Pasting Editable Gantt OLE from Project 2007 Into PowerPoint 2007
When I insert the linked OLE object, PowerPoint always defaults to object size 1.68 inches x 4.9 inches, which is only large enough to show the top left corner. When I resize the object, it just stretches the current view by resizing the font and sizes of cells. Opening the object and editing in Project changes... 8 Dec 2009 16:27
highlight changes in a different colour
How can i highlight changes to Project in a different colour automatically!? ... 8 Dec 2009 10:49
Project Stand Alone - tasks hidden
This has me stumped. I have a project manager that copied and pasted task names from one project to another and then entered all the other information. However after saving, closing and reopening the project the newly copied/pasted tasks don't display and show the ID number as 60, 61, 62, 63, 70, 71, 72 and... 8 Dec 2009 13:04