Hinding/Deleating Resource information before sending
hi, i have to send my MS project file to an customer. He is just interested on the timetable (the processes, the start- and enddates as well as the links). However, i put also the resouce information into these processes. Therefore, is there a way, to hide/delete these information about the reseources before is... 18 Jan 2010 09:46
Copy Internal Links when Copying a Summary Tasks
In some projects, when I copy a summary task it copies the links between its subtasks. In others, the links are not copied. What controls if the links are copied or not? 10x, Barak Submitted via EggHeadCafe - Software Developer Portal of Choice Understanding .NET http://www.eggheadcafe.com/tutorials/a... 18 Jan 2010 05:21
Customising Gantt Bar appearances based on milestone they fall in
I have four milestones dates defined for my project. I'd like to have some way of displaying which milestone a task is completed during. My preferred way would be to change the colour of the Gantt bar (or the task name) depending upon which Milestone it completes during. I have no idea how to do this (I'm... 16 Jan 2010 17:15
Linking projects
Hello, side question on the insert project function. in msp 2007 it automatically links the 2 projects. Is there a way to insert a project without automatic link between the 2 files being created. Thanks, Stephane -- Stephane ------------------------------------------------------------------------ Stephane's ... 18 Jan 2010 04:16
how to sizes paper for quarter ad for souvenir booklet
Doing a souvenir booklet and have some quarter page ad. How do I sizes the paper ... 16 Jan 2010 10:37
Tracking Gantt display config
Can I flip the Scheduled vs Actual bars - Scheduled on top/Actual on the bottom? Pete ... 15 Jan 2010 23:50
Resource allocation
Is it best to define resource by role or by individual person? I have a number of tasks which are essentially project management but are being carried out by different people, some of them solution architects. These people have different global cost rates. Or is it possible to assign a cost to an individual task? I ne... 17 Jan 2010 08:21
MSProject 2003 Kicking End Dates Way Out
I am having a problem with MSProject moving task end dates way out into the future, even though I haven't changed duration, nor have I resource leveled the task. For example, an 80-hour task, fixed work, 75% complete, with resources working full time ends up with an end date getting kicked out several months. It's n... 15 Jan 2010 08:16
Anyone have MS Project Plan for Planning/Executing a Golf Tourname
I created one a long time ago according to the PGA recommended guidelines and checklists. It was a lot of work so I'd like not to have to reinvent the wheel... ... 14 Jan 2010 15:50
XPS disply problem
I cant disply XPS documents form the link http://websvn.companydomain.local/filedetails.php?repname=Documents&path=%2FDevelopment%2FBatch+2%2FProject+Plan%2Fbatch2+v1.0.xps It starts IE but keeps it blank. If I go directly on my local machine there is not a problem. I put right MIME: application/vnd.ms-xpsdo... 14 Jan 2010 11:19