Prev: Copy Picture
Next: Personal Views
From: strach on 31 Mar 2010 02:47 I definitely was, and it seems I just found the solution. Looks like the successor task is not lined up sequentially after predecessor due to setting non-zero value for "% complete" to successor. Once I set it back to zero it works fine again. Thanks for your support, strach "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message news:e7ToFDG0KHA.4384(a)TK2MSFTNGP06.phx.gbl... > Strach, > Are you using F to Start links? > I hope this helps. Let us know how you get along. > Julie > Project MVP > Visit http://project.mvps.org/ for the FAQs and additional > information about Microsoft Project > On 3/30/2010 6:08 PM, strach wrote: >> Hello guys, >> I have the same problem, calculation mode is automatic and constraint in >> successor task is by default As Soon As Possible. I'm using MS Project >> 2002. >> TIA >> strach >> "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message >> news:OtAOgOA0KHA.2436(a)TK2MSFTNGP04.phx.gbl... >>> Hi Tonyjstark, >>> Check your calculation settings. Should be automatic -- see Tools > >>> Options, Calculation tab. >>> I hope this helps. Let us know how you get along. >>> Julie >>> Project MVP >>> Visit http://project.mvps.org/ for the FAQs and additional >>> information about Microsoft Project >>> On 3/30/2010 8:09 AM, Tonyjstark wrote: >>>> I am using M/S project 2000 and my task dependencies are not shown >>>> correctly on my gantt chart. eg if I enter a task with another being a >>>> predecessor with a finish to start type dependency and it shows the >>>> two taks starting in parrallel or even before the other one has >>>> finished. >>>> I am not a beginner to M/S project but have never seen this before. I >>>> guess I have set something within the project which has resulted in >>>> this but don't know where to look. >>>> Any ideas?
From: JulieS on 31 Mar 2010 12:27
Hi Strach, Thanks for the update and the explanation of what was causing the error. To clarify for anyone else reading along, when Strach talks about a non-zero % complete, the issue was that once a task has even 1% complete marked against it, the task also has an Actual Start date. Once a task has an Actual Start date, it will not longer respond to changes in predecessors. By setting the % complete back to zero, you removed the Actual Start date. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 3/31/2010 2:47 AM, strach wrote: > I definitely was, and it seems I just found the solution. Looks like the > successor task is not lined up sequentially after predecessor due to > setting non-zero value for "% complete" to successor. Once I set it back > to zero it works fine again. > > Thanks for your support, > strach > > "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message > news:e7ToFDG0KHA.4384(a)TK2MSFTNGP06.phx.gbl... >> Strach, >> Are you using F to Start links? >> I hope this helps. Let us know how you get along. >> Julie >> Project MVP >> Visit http://project.mvps.org/ for the FAQs and additional >> information about Microsoft Project >> On 3/30/2010 6:08 PM, strach wrote: >>> Hello guys, >>> I have the same problem, calculation mode is automatic and constraint in >>> successor task is by default As Soon As Possible. I'm using MS Project >>> 2002. >>> TIA >>> strach >>> "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message >>> news:OtAOgOA0KHA.2436(a)TK2MSFTNGP04.phx.gbl... >>>> Hi Tonyjstark, >>>> Check your calculation settings. Should be automatic -- see Tools > >>>> Options, Calculation tab. >>>> I hope this helps. Let us know how you get along. >>>> Julie >>>> Project MVP >>>> Visit http://project.mvps.org/ for the FAQs and additional >>>> information about Microsoft Project >>>> On 3/30/2010 8:09 AM, Tonyjstark wrote: >>>>> I am using M/S project 2000 and my task dependencies are not shown >>>>> correctly on my gantt chart. eg if I enter a task with another being a >>>>> predecessor with a finish to start type dependency and it shows the >>>>> two taks starting in parrallel or even before the other one has >>>>> finished. >>>>> I am not a beginner to M/S project but have never seen this before. I >>>>> guess I have set something within the project which has resulted in >>>>> this but don't know where to look. >>>>> Any ideas? > > |