From: Tonyjstark on 30 Mar 2010 08:09 I am using M/S project 2000 and my task dependencies are not shown correctly on my gantt chart. eg if I enter a task with another being a predecessor with a finish to start type dependency and it shows the two taks starting in parrallel or even before the other one has finished. I am not a beginner to M/S project but have never seen this before. I guess I have set something within the project which has resulted in this but don't know where to look. Any ideas?
From: Jan De Messemaeker on 30 Mar 2010 08:18 Hi, It sounds like you havev a constraint on the successor task (Finish no later than or must finish on) -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Tonyjstark" <Tonyjstark(a)discussions.microsoft.com> wrote in message news:DD3A96B7-69C1-4AA5-828F-F6E48F52B550(a)microsoft.com... >I am using M/S project 2000 and my task dependencies are not shown >correctly > on my gantt chart. eg if I enter a task with another being a predecessor > with > a finish to start type dependency and it shows the two taks starting in > parrallel or even before the other one has finished. > > I am not a beginner to M/S project but have never seen this before. I > guess > I have set something within the project which has resulted in this but > don't > know where to look. > > Any ideas?
From: JulieS on 30 Mar 2010 08:22 Hi Tonyjstark, Check your calculation settings. Should be automatic -- see Tools > Options, Calculation tab. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 3/30/2010 8:09 AM, Tonyjstark wrote: > I am using M/S project 2000 and my task dependencies are not shown correctly > on my gantt chart. eg if I enter a task with another being a predecessor with > a finish to start type dependency and it shows the two taks starting in > parrallel or even before the other one has finished. > > I am not a beginner to M/S project but have never seen this before. I guess > I have set something within the project which has resulted in this but don't > know where to look. > > Any ideas?
From: strach on 30 Mar 2010 18:08 Hello guys, I have the same problem, calculation mode is automatic and constraint in successor task is by default As Soon As Possible. I'm using MS Project 2002. TIA strach "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message news:OtAOgOA0KHA.2436(a)TK2MSFTNGP04.phx.gbl... > Hi Tonyjstark, > Check your calculation settings. Should be automatic -- see Tools > > Options, Calculation tab. > I hope this helps. Let us know how you get along. > Julie > Project MVP > Visit http://project.mvps.org/ for the FAQs and additional > information about Microsoft Project > On 3/30/2010 8:09 AM, Tonyjstark wrote: >> I am using M/S project 2000 and my task dependencies are not shown >> correctly on my gantt chart. eg if I enter a task with another being a >> predecessor with a finish to start type dependency and it shows the >> two taks starting in parrallel or even before the other one has finished. >> I am not a beginner to M/S project but have never seen this before. I >> guess I have set something within the project which has resulted in >> this but don't know where to look. >> Any ideas?
From: JulieS on 30 Mar 2010 19:28
Strach, Are you using F to Start links? I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 3/30/2010 6:08 PM, strach wrote: > Hello guys, > > I have the same problem, calculation mode is automatic and constraint in > successor task is by default As Soon As Possible. I'm using MS Project > 2002. > > TIA > strach > > "JulieS" <JulieS(a)discussions.microsoft.com> wrote in message > news:OtAOgOA0KHA.2436(a)TK2MSFTNGP04.phx.gbl... >> Hi Tonyjstark, >> Check your calculation settings. Should be automatic -- see Tools > >> Options, Calculation tab. >> I hope this helps. Let us know how you get along. >> Julie >> Project MVP >> Visit http://project.mvps.org/ for the FAQs and additional >> information about Microsoft Project >> On 3/30/2010 8:09 AM, Tonyjstark wrote: >>> I am using M/S project 2000 and my task dependencies are not shown >>> correctly on my gantt chart. eg if I enter a task with another being a >>> predecessor with a finish to start type dependency and it shows the >>> two taks starting in parrallel or even before the other one has >>> finished. >>> I am not a beginner to M/S project but have never seen this before. I >>> guess I have set something within the project which has resulted in >>> this but don't know where to look. >>> Any ideas? > > |