are there templates for layout of fitted kitchen using drawing.
there used to be a template for layout drawing for kitchen and office designing on office 3. is there on e in office 7 ... 17 May 2010 06:57
Email Notification Project 2007
When I use the File/Send To/Mail Recipient options the program is having trouble picking up the correct email address. It is trying to access our state global address list. It does not recognize the resource name even if I seperate multiple resources with commas. It tries to grab the first or last name and m... 14 May 2010 17:14
how can I print start & finish dates
I am unable to get the rows for start & finish dates to actually show the dates and to print in calendar. The printout shows the rows, but without any dates. ??? ... 14 May 2010 18:20
Formula
I am pretty weak on formulas but here goes. I have the following formula: IIf([Duration]=0,(IIf([% Complete]=100,2,IIf([Finish]<Now()+14 And [% Complete]<100 And [% Complete]>=80,3,IIf([Finish]<Now()+14 And [% Complete]<80,4,1)))),IIf([% Complete]=100 Or [% Complete]>100*(Abs((Now()-[Start])/([Finish]-[Start])))... 14 May 2010 13:56
Start, Finish and Duration Changes in MS Project 2003?
Hi We are using MS Project 2003. I see the start, finish and duration in a project schedule changes with respect to the project progress. Why does this happen? Thank you Chaitanya. ... 14 May 2010 09:30
IMport assignment from Project to Outlook
Dear Alll I don't know if this is the right forum, but i really need an advice. I need to import all my MS Project Assingments to MS Outlook!! I have checked on other wen pages but nothing with good information. I would like to ask you all out there if someone can help. regards ... 14 May 2010 09:30
Microsoft Office One Note - USB
Hej Jeg har lavet en one notes book på min hjemme computer. vil gerne kunne bruge denne via USB Stik på arbejdscomputer, så jeg kan bruge mine data der. Kan det ikke lade sig gøre? ... 14 May 2010 06:16
Drop Down Menu
Hi there, I'm really sorry if this has been answered, but I need some help. I just started using MS Project last week, and I need to create a drop-down menu in a text field (in other words, I need for users of our schedule to only be able to select certain answers to a question so that we can then sort and r... 13 May 2010 21:36
how do i get tasks to move out days as they become past due?
so as the date slides... i would like the attached downstream tasks to slide also(day for day). this would give me a more accurate idea of what my finish date to the customer would be. the version i am using is 2003. ... 13 May 2010 20:30
Task Delaying start
What would cause a task to delay its start from its predecessor if there is no lag and no resource contention. I have 2, 3day tasks for a resource that are not lined up back to back. The second is waiting three days to start. And yes, I have a new version of project that is not completely set up to my likin... 13 May 2010 20:30