Merging file : Problem with external links Hello, When I try to merge different project file (by Insert-->Project), I still see the external link between project (in gray color). My purpose is to have a single file for which all the tasks are linked inside the same document and not on the old file. How can i do? Thanks ... 6 May 2010 10:48
Frozen Assignment units in Proj Pro 2010 Hi folks, since I work on the final RTM Project Profesional 2010, I face a new issue. When you define a single task "Fixed Duration" with a single assignment full time, the assignment units does not react as it should. As a matter of fact, when this option is set with OK. Then, in a second step, you moved t... 5 May 2010 09:20
MSP updates actual work when editing work in resource usage view Hi, we recently switched to a master project arrangement for all our projects, which brought on the need to use resource usage view to hand edit the distribution of remaining work for each resource/task. This has generally worked fine, except recently we've found this very annoying problem - when we alter the... 5 May 2010 09:20
change displayed milestone date? I would like to change the date displayed against milestones from day/month (default setting) to month/year. How is this done? ... 5 May 2010 20:31
Adding Costs to Tasks Hi There - I am trying to add costs to different tasks and for some reason they are not adding up. My column is fixed cost; any suggestions? ... 7 May 2010 17:52
([Finish Variance]/ ProjDateDiff(Phase Start,Phase Finish)) Obviously this ([Finish Variance]/ ProjDateDiff(Phase Start,Phase Finish)) does not work because I can't figure out how to capture Phase start and finish in the formula. I want to report on indivdual phase health by comparing Finish Variance to phase duration. This alternative ([Finish Variance]/(ProjDateDiff... 5 May 2010 18:18
Recording a macro When I try and record a macro I get an error message saying "File not found". Yet if I look at the organizer--> modules it has created a new modules which you cannot delete. any ideas? -- Sharktracker ... 6 May 2010 15:24
Interim plans I am trying to better understand saving an interim plan. The question: Once I save an interim plan, where does it go? It doesn't appear to be saved as a separate file. If I read the M'soft help, it appears that the only way I can see it is to insert the Start1 and Finish1 columns in my project. True? Also, what... 4 May 2010 12:21
assignment units "Fixed Units Indicates that the task's number of assignment units must remain constant, regardless of any change in duration or work for the task. This is the default. For fixed-unit tasks:" What is "assignment units" means here ? Could you please explain ? Thanks KS ... 4 May 2010 12:21
Merging different project Dear All, I have developped 10 different projects that are linked together. My goal is to merge all the planning into one file. The "copy past" way is not the best practise as there are problems with external links. Does anyone know a macro or a program or a trick to merge all the file. Thanks a lot for your... 4 May 2010 14:35 |